Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T05CM05372
Parcel: 12709012C

Review Status: Completed

Review Details: CELL TOWER/ANTENNAS

Permit Number - T05CM05372
Review Name: CELL TOWER/ANTENNAS
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/26/2005 ALINE TORRES PLANNING-CITY HALL REVIEW Approved
10/31/2005 JIM EGAN FIRE REVIEW Approved
11/06/2005 PATRICIA GILBERT ENGINEERING REVIEW Approved
11/08/2005 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov
IF YOU CARE TO DISCUSS.

1. It appears that the intent is to provide a single-phase panel as Panel A. Please clarify on the panel schedule itself, which indicates that this is 3 phase.
2. Specify the number of poles for the new Circuit Breaker on the transformer primary.
3. Specify the fault current rating for this Breaker. Note that TEP Available Fault Current for a 480/277V service 800-1600A 32,600 AFC, unless their Engineer tells you otherwise.
4. Circuit A-16,18, on a 40A CB, has no load. Please clarify.
11/11/2005 CRAIG GROSS ZONING REVIEW Approved
11/22/2005 CHRISTY FOREMAN BUILDING-COMMERCIAL REVIEW Denied CITY OF TUCSON DEVELOPMENT SERVICES
STRUCTURAL REVIEW COMMENTS

DATE: 11/23/05
ACTIVITY NUMBER: T05CM05372
PROJECT NAME: Verizon Wireless
PROJECT ADDRESS:. 6245 E. Broadway Bl
ARCHITECT / ENGINEER: Kenneth Camp
PROJECT REVIEWER: Christy Foreman


TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1108 OR EMAIL AT CFOREMA1@CI.TUCSON.AZ.US IF YOU CARE TO DISCUSS.

1) Sht. A-3 conflicts with sht. A-2. Note on A-3 specifies new 6'-0" antenna mounted to existing parapet sht. A-2 specifies 8'0".
2) Sht. A-3 conflicts with Sht. A-2. Note on A-3 specifies new verizon wireless equipment cabinet on new platform. Sht. A-2 specifies new equipment cabinet mounted to existing platform.
3) Special Inspection form for field welding will need to be submitted before permit can be issued.
4) Please provide drawing with structural calculations clarifying location of each additional load being justified.
5) Please justify / clarify IBC 2003 code section for acceptable increase specified on page 2 of structural calculations.
11/25/2005 JAY HOGAN OPERATIONS REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
12/13/2005 CINDY AGUILAR OUT TO CUSTOMER Completed
12/13/2005 SUE REEVES REJECT SHELF Completed