Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T05CM05080
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/20/2006 | ANDREW CONNOR | NPPO | REVIEW | Denied | Submit completed application for exception form including acceptable documentation, which clearly indicates that the project will not impact Protected Native Plants. Such documentation includes photographs of the site taken from all sides of the property and a signed statement from the property owner that Protected Native Plants are not located on the subject site. Photographs of the site are necessary for NPPO approval per DS 2-15.2.0.C. |
| 03/30/2006 | PATRICIA GILBERT | ENGINEERING | REVIEW | Denied | DATE: March 31, 2006 ACTIVITY NUMBER: T05CM05080 PROJECT NAME: Schulte Duplex PROJECT ADDRESS: 3530 E. Monte Vista PROJECT REVIEWER: Patricia Gilbert, Engineering Associate The following items must be revised or added to the site plan. Please include a response letter with the next submittal that states how all comments have been addressed. RESUBMITTAL REQUIRED: SITE PLAN 1. It is acknowledged that John Clark of Environmental Services has accepted the current proposal. However in the letter from John Clark dated October 7th, 2005, he clearly states, "Side wall protection is required with a clear area of 10' by 10'." Detail B1 on sheet C1.1 does not show side wall protection. Per DS 6-01.4.2.C.2. steel pipes are required at the side walls of a solid waste enclosure. Please indicate steel pipes at the side walls of the solid waste enclosure, be aware the concrete slab (10' by 10' clear area) will need to increase in size to accommodate the steel pipes. |
| 03/30/2006 | LINHART PETERSEN POERS ASSOC. | 2ND PARTY REVIEW | REVIEW | Approved | |
| 05/13/2006 | DAVID RIVERA | ZONING | REVIEW | Denied | 05/13/06 Development Services Department Zoning Review Section David Rivera Principal Planner Comments: 1. Zoning has reviewed the building plans but cannot approve them at this time until the plans have been completely approved through the commercial review process. 2. A site card with DSD approvals by Fire, Zoning, Handi-cap, Engineering, and Landscape/NPPO including the approved development plan stamped for site plan approval and signatures is required before the grading plan can be approved by Zoning. Two copies of the CDRC approved tentative plat/development plan, landscape and NPPO plans are to be submitted with the grading plan packet for processing and approval as a site plan. No fees are involved in re-stamping the development/tentative plat plans as an approved site plan. The tentative plat/development plan may be walked through for stamps and site card sign off. Submit the following: two copies of the stamped development plan, landscape and NPPO plans must be included with the grading plans packet processed together for site approval. 3. Zoning will re-review and approve the building plans on the next submittal providing the stamped and approved site plans are included with the building plan package and the building structural portions of the plan review have been approved. See comment 2 for additional info regarding the site plan process. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 05/18/2006 | ADRIANNE OLIVO | OUT TO CUSTOMER | Completed |
| 05/18/2006 | SUE REEVES | REJECT SHELF | Completed |