Permit Number: T05CM04748
Parcel: 10511061R

Review Status: Completed

Review Details: COMMERCIAL TI

Permit Number - T05CM04748
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/16/2005 JIM EGAN FIRE REVIEW Approved
09/26/2005 RAUL PALMA BUILDING-COMMERCIAL REVIEW Denied 1) Provide connection details of TV to supports.
2) Delete MESA or anyting relating to MESA and instead show TUCSON or CITY OF TUCSON.
09/30/2005 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Approved
09/30/2005 ROBERT SHERRY WATER REVIEW Approved
10/12/2005 SREEVES1 WWM REVIEW Passed No plbg
10/18/2005 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov
IF YOU CARE TO DISCUSS.

1. Circuit L-25 has been used the sign, but this circuit is a spare on the panel schedule.
2. Please include a load of 200 VA /LF for the Show Windows on Ckt L-1, if this is the intent. Reference NEC 220.12 (A).
3. With 400W MH lighting per the Light Fixture Schedule, Ckts L-2, L-4, and L-6 should be counted as 1600 VA each. Verify that all lighting and sign electrical loads are counted at 1.25% in the Load Summary, and carry the calculations through the transformer.
4. It appears that the load on Panel L is 33.1 KVA, which may overload the 30 KVA X'FMR. This considers the track lighting, and other lighting at 1.25%. Does not include sign. See Comment #1 above.
5. Provide load calculations to demonstrate that service and any distribution panels are not overloaded.
6. Electrical Specifications Fire Alarm System Notes are not necessary, because the the system is covered on Sheet E-1, and such notes are furthermore incorrect because they imply that the Contractor may design such a system, which would not be permitted in this jurisdiction. Note that Fire has approved this set for construction.
7. Electrical Specifications Method and Materials Note 17 refers to NEC 250-72. No such section on the 2002 NEC.
8. Electrical provides power for a Water Heater. Plans do not include Plumbing. Please coordinate with other disciplines and clarify.
10/18/2005 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied Provide the specifications and listing information for the water heater being installed (sheets E-1 and E-4). Show how the unit is to be installed. Reference Section 103.2.3, UPC 1994.

Final Status

Task End Date Reviewer's Name Type of Review Description
11/02/2005 GBONILL1 OUT TO CUSTOMER Completed
11/02/2005 GBONILL1 REJECT SHELF Completed