Review Status: Completed
Review Details: SITE
Permit Number - T05CM04519
Review Name: SITE
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/30/2005 | ANDREW CONNOR | LANDSCAPE | REVIEW | Passed | |
09/30/2005 | ANDREW CONNOR | NPPO | REVIEW | Passed | |
10/13/2005 | DAN CASTRO | ZONING | REVIEW | Approved | COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. The most recent approved site plan is required for reference. The submittal package included a plan for a propane tank, which is not a site plan. The site plan is necessary to verify what existing site conditions, if any, will be affected by this project. 2. On sheet A-1 "site plan", provide the vehicle parking calculation for the existing use. If retail, the site shall be parked at one (1) space per 200 square feet of gross floor area. The calculation shall include the use, gross floor area, parking ratio, number of vehicle parking spaces required and provided. Refer to LUC Sec. 3.3.4 for vehicle parking requirements. 3. Additional site review comments may be required if there are significant changes shown on the most recent approved site plan and the site plan included for this project. If you have any questions about this transmittal, please call Dan Castro, (520) 791-5608 ext. 1180. An appointment is required to discuss these comments in person. |
10/14/2005 | DAN CASTRO | ZONING HC SITE | REVIEW | Passed | refer to zoning review comments |
11/07/2005 | PAUL MACHADO | ENGINEERING | REVIEW | Approved |