Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL NEW
Permit Number - T05CM04401
Review Name: COMMERCIAL NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/26/2005 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide supporting documentation for the assembly U-factors for the window walls, skylights and the roof along with the SHGC for the window walls and the skylights. Reference Section 104.2, IECC 2000. 2. Specify the minimum resistance (R-value) of the duct insulation to be used on this project. Reference Section 803.2.8, IECC 2000. 3. Provide structural calculations to verify that the existing roof is capable of supporting the additional dead load due to the installation of the roof top units. Reference Section 302.1, IMC 2000. 4. Provide calculations demonstrating adequate ventilation. Reference Section 401.2, IMC 2000. 5. Provide information to show how the concentration of CO2 in the space can be related to a specific ventilation rate. Reference Section 106.3.1, IMC 2000. 6. Provide information on the sequence of operation for the restroom exhaust to show that recirculation of the air from the restroom will not occur. Reference Section 403.2.1, IMC 2000. 7. Clarify that the smoke detectors shall be located upstream of any outside air connections. Reference Section 606.2.1, IMC 2000. |
| 08/26/2005 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 08/29/2005 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Revise the font size used on the drawings to a minimum of 10 points. Reference Section 302.3, Uniform Administrative Code, 1997. 2. Revise the design of the vented sleeve for the natural gas so that the vent terminates above grade but in an area outside the building where any leakage can be readily detected (i.e. leakage can be smelled by people walking by the vent). Show that the termination of the sleeve inside the building is in a usable and accessible portion of the building. Reference Section 6.1.6, NFPA 54 - 2002. 3. Specify the polyethylene pipe to be used for the gas piping. Reference Section 103.2.3, UPC 1994. 4. Provide a detail of the water heater installation, including the excess pressure relief, expansion tank, and valves. Reference Section 103.2.3, UPC 1994. 5. Show how the water heater is to be supported above the mop sink. Reference Sections 103.2.3 and 511.2, UPC 1994. 6. Specify the thickness and maximum conductivity of the pipe insulation. Reference Section 804.5, IECC 2000. 7. City of Tucson Ordinance 1802 requires a reduced pressure backflow preventer to be located immediately after the water meter. Please show the RPBP on the drawings and include the pressure drop on the water calculations. Reference Section 103.2.3, UPC 1994. 8. Coordinate the water isometric on sheet P2.0 with the piping layout shown on the floor plan (Sheet P1.0). Reference Section 103.2.3, UPC 1994. 9. Clarify the position of the remote chiller for the drinking fountain; In the Janitor's room or under the sink counter? Provide an installation detail to show that the unit is being installed per the product listing. Reference Section 301.1.1, UPC 1994. 10. One of the specified fixtures (American Standard pressure-assisted water closet) requires a minimum pressure greater than the 15-PSI used in the water pipe sizing calculations (Table 6-4). Revise the calculations as necessary to include the additional required pressure. Reference Section 608.1, UPC 1994. 11. Revise the static lift used for the water pressure calculations to correspond to the actual conditions (e.g. the hose bibb located approximately 17-feet above the water meter). Reference Section 610.7 (3), UPC 1994. 12. Tucson Water shows an available pressure range of 47 to 54-PSI for the project address, not 65-PSI as shown in the provided calculations. Revise the calculations and pipe sizes as required. Reference Section 610.7 (5), UPC 1994. 13. The two-way cleanout depicted on the waste isometric (sheet P2.0) appears to violate Section 707.6, UPC 1994, which requires each cleanout fitting to be installed in the direction of flow. An approved two-way cleanout fitting (Section 707.4 (5), UPC 1994)is not the same as two combination wye fittings installed with one fitting reversed to form a two-way cleanout. |
| 08/30/2005 | JIM EGAN | FIRE | REVIEW | Approved | |
| 09/07/2005 | GERRY KOZIOL | WWM | REVIEW | Denied | needs to review location & method of connection to public sewer |
| 09/20/2005 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL. PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov IF YOU CARE TO DISCUSS. 1. Demonstrate compliance with the Tucson Lighting Code, http://www.tucsonaz.gov/dsd/Codes___Ordinances/Tucson_Lighting_Code.pdf. 2. Please enlarge font size as necessary, to 10 point. 3. Insert load information on Panel Schedule for Ckt A-2 (LV Exterior Lighting), Ckts B-34 and B-36 (Customer Lounge Receptacles), Ckts B-34 and B-36 (Cash Room). Note that B-34 and B-36 were used twice, not a Code issue, but it may not be the intent. 4. Water Heater listed on Sheet E3 Keynote 65 as single phase, but is on Ckt A-3,5 according to the Power Plan. It is on Ckt A-35 on the Panel Schedule. 5. Having the building service mounted on a nearby wall does not strictly meet the requirements of NEC 225.30. However, since the panels are grouped such that the mains on the panels can serve as the disconnects, the feeders come in together, and are a minimum 1/0, the configuration appears to meet the intent. In this case, a separate grounding electrode needs to be established at the panels to fulfill the requirements of NEC 250.32. |
| 09/21/2005 | RAUL PALMA | BUILDING-COMMERCIAL | REVIEW | Denied | 1) Specify the thickness of the base plate on all the structural details. 2) Calcs specify a 7'-6" embedment into soil, but plans show 6' min. Also the diameter per calcs shall be 30" instead of 24". 3) Deferral of any submital item(s) shall have the prior approval of the building official. |
| 09/23/2005 | PAUL MACHADO | ENGINEERING | REVIEW | Denied | Flood Plain Use permit required. |
| 09/30/2005 | DAN CASTRO | ZONING | REVIEW | Denied | To review the building plans, the Zoning Review section requires that a copy of the stamped approved development plan/site plan be included in each building plan set. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/04/2005 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |
| 10/04/2005 | CINDY AGUILAR | REJECT SHELF | Completed |