Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - SITE ALL
Permit Number - T05CM04242
Review Name: RESUBMITTAL - SITE ALL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/15/2007 | PATRICIA GILBERT | ENGINEERING | REVIEW | Denied | DATE: March 19, 2007 ACTIVITY NUMBER: T05CM04242 PROJECT NAME: Living Waters Ministry PROJECT ADDRESS: 4343 East 22nd Street PROJECT REVIEWER: Patricia Gilbert, Engineering Associate The following items must be revised or added to the site plan. Please include a response letter with the next submittal that states how all comments have been addressed. RESUBMITTAL REQUIRED: SITE PLAN 1. This comment was not addressed/corrected. After reviewing a ROW plan it appears the ROW is not built out to the future ROW, i.e. future curb and sidewalks. Consequently the label for the future ROW 75' dimension should only be labeled, "future ROW." Verify with the Department of Transportation that the existing ROW is not built out to the future ROW. If the existing ROW is not built out to future, revise the label on the plan to remove the word "existing". In the response letter clarify your findings. A response letter was not submitted 2. Per a new Development Services policy, sidewalks are required on all new development. Provide a new 6' sidewalk on the site plan. It is acknowledged that a call out for future sidewalk is on the plan view. However it is not clear if the sidewalk is going to be built. Clearly indicate on the plan view new/proposed 6' sidewalk along 22nd Street. 3. This comment was not addressed/corrected. Revise the near side site visibility triangle length to the required length of 345'. DS 3-01.5.0. 4. This comment was not addressed/corrected. The refuse enclosure detail (5/A1) must show an inside clear dimension of ten (10) feet by ten (10) feet between the Steel pipes/bollards. Revise the detail as necessary. D.S. 6-01.4.2. |
03/20/2007 | TERRY STEVENS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Terry Stevens FOR: David Rivera Senior Planner Principal Planner PROJECT:T05CM04242 4343 E. 22nd St. Modular Building Site Plan Transmittal date:4th Review 3/20/07 COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1.The provided last approved site plan indicates the public use area as 3855 sq. ft. If this is correct a total of 77 parking spaces are required. If the assembly area of the building is 1806 sq. ft. as indicated on the site plan provide a dimensioned floor plan clearly indicating such. It appears that a tax parcel lot combination has been completed. Provide a copy of the lot combination documentation. A Covenant Regarding Development and Use of Real Property will be required to be completed and recorded. Provide recordation information (docket and page) on the site plan. This form is available on line at the DSD web site. 2.DS 2-02.2.1.9 For off street bicycle parking provide the full dimensioned layout including the required access aisle, detail of specific type of rack and number of bicycles it supports. Bicycle parking calculations indicate 4 class 2 required, detail and site plan indicate only 2 being provided. Clarify. Clarify the location of the directional signage on page A1 for the bicycle parking spaces. It appears to be located in the middle of the sidewalk? 3.Clearly indicate the minimum distance from grade to the bottom of the handicap parking sign as 7'-0" as per City of Tucson standards. 4.Based on responses to comments and changes to the plans further comments may be forth coming. If you have any questions about this transmittal, please call Terry Stevens, (520) 791-5550 ext. 2000. |
03/20/2007 | TERRY STEVENS | ZONING HC SITE | REVIEW | Denied | see zoning comments |
03/20/2007 | ANDREW CONNOR | LANDSCAPE | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
04/10/2007 | GERARDO BONILLA | OUT TO CUSTOMER | Completed |
04/10/2007 | SUE REEVES | REJECT SHELF | Completed |