Permit Number: T05CM02884
Parcel: 12419079B

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T05CM02884
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/05/2005 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. The area used to calculate the ventilation for room 105 (AC-3) does not agree with the dimensioned architectural plans. Revise the ventilation calculations demonstrating as required. Reference Section 403.3, IMC 2000.
2. The owner is paying for power to be installed for a range in the snack bar (Circuits 12 and 14, Panel S). It is therefore a valid assumption that a range is planned for that area. A Type 1 hood will be required for that range.
10/06/2005 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Comment not addressed. Increase the size of the overflow in the roof drain collector box to equal the size of the scupper. Reference Section D1.1 (d), UPC 1994.
2. Correct the arithmetic for the total water fixture units and recalculate the total demand. Correct the arithmetic for the allowable pressure loss per 100 feet in the water calculation. Revise the pipe sizes if required. Reference Section 610.1, UPC 1994.
3. A 3" trap (P9B) has 6 waste fixture units. Reference Section 702.0 and Footnote, Table 7-3, UPC 1994.
4. The fixture connection sizes called out for the flush valves will result in water velocities greater than 8 FPS. Limit the water velocity to less than 8 FPS for the copper piping. Reference Section A 6.1, UPC 1994 and IAPMO IS 3-93, Section 610.0.
5. Coordinate the mechanical and plumbing equipment requirements with the electrical designs (e.g. EC-1 is not a 3/4HP pump and only there is one water heater, not two). Include the specifics of RCP-1 on the drawing.
10/14/2005 RAUL PALMA BUILDING-COMMERCIAL REVIEW Approv-Cond
10/17/2005 GERRY KOZIOL WWM REVIEW Denied needs 8th floor credit evaluation
10/19/2005 BOB SUBA ELECTRICAL-COMMERCIAL REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
10/25/2005 KMEDINA1 OUT TO CUSTOMER Completed