Permit Number: T05CM02884
Parcel: 12419079B

Review Status: Completed

Review Details: COMMERCIAL NEW

Permit Number - T05CM02884
Review Name: COMMERCIAL NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/23/2005 JIM EGAN FIRE REVIEW Approved
06/23/2005 GERRY KOZIOL WWM REVIEW Denied needs 8th floor credit evaluation
06/28/2005 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Provide updated energy code compliance calculations. Reference Section 101.3, International Energy Conservation Code 2000.
2. Provide calculations demonstrating adequate ventilation. Reference Section 401, IMC 2000.
3. Electrical panel "S" provides power for a range. A Type 1 hood will be required for that range.
06/28/2005 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Increase the size of the overflow in the roof drain collector box to equal the size of the scupper. Reference Section D1.1 (d), UPC 1994.
2. Provide the referenced Civil drawing to show the continuation of the site utilities and storm drains. Reference Section 103.2.3, UPC 1994.
3. Include all fixtures (e.g. whirlpools and ice machine) and the water requirements of the HVAC equipment when calculating the total demand and determining pipe sizes. Reference Section 610.1, UPC 1994.
4. Include the static lift when performing the water pressure calculations. Reference Appendix A, UPC 1994.
5. Show how the fan-assisted flue for the water boiler was sized. Reference Section 103.2.3, UPC 1994
6. Provide upper terminal cleanouts on horizontal drainage pipes exceeding 5 feet in length (horizontal drain lines serving sinks and urinals require cleanouts regardless of length). Reference Section 707.4, UPC 1994.
7. Modify trap arm lengths to conform to Table 10-1, UPC 1994 with AZ State amendments.
8. Show the size of the runouts to the urinals and the water closets. Reference Section A6.1, UPC 1994.
9. Clarify the apparent disparity between the two boiler control and three pump circuits shown on electrical panels "S" and "P" and the plumbing design.
06/28/2005 ROBERT SHERRY WATER REVIEW Approved
06/30/2005 BOB SUBA ELECTRICAL-COMMERCIAL REVIEW Denied 1.Provide a complete single line diagram showing all conduit and conductor sizes,transformers,grounding, and over current protection,fault current etc.
07/15/2005 RAUL PALMA BUILDING-COMMERCIAL REVIEW Denied . City of Tucson, Development Services
BUILDING AND STRUCTURAL COMMENTS

1) Page 8c of the calcs under STEM CONSTRUCTION shows top stem and 2nd stem.
Under top stem is shown 2 foot stem and under 2nd stem is shown 0' , but theheight
of wall is supposed to be 8.67 ft. Clarify!

Final Status

Task End Date Reviewer's Name Type of Review Description
07/26/2005 SUE REEVES OUT TO CUSTOMER Completed
07/26/2005 ANGIE SHOFFSTALL REJECT SHELF Completed