Review Status: Completed
Review Details: COMMERCIAL NEW
Permit Number - T05CM02884
Review Name: COMMERCIAL NEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/23/2005 | JIM EGAN | FIRE | REVIEW | Approved | |
06/23/2005 | GERRY KOZIOL | WWM | REVIEW | Denied | needs 8th floor credit evaluation |
06/28/2005 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide updated energy code compliance calculations. Reference Section 101.3, International Energy Conservation Code 2000. 2. Provide calculations demonstrating adequate ventilation. Reference Section 401, IMC 2000. 3. Electrical panel "S" provides power for a range. A Type 1 hood will be required for that range. |
06/28/2005 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Increase the size of the overflow in the roof drain collector box to equal the size of the scupper. Reference Section D1.1 (d), UPC 1994. 2. Provide the referenced Civil drawing to show the continuation of the site utilities and storm drains. Reference Section 103.2.3, UPC 1994. 3. Include all fixtures (e.g. whirlpools and ice machine) and the water requirements of the HVAC equipment when calculating the total demand and determining pipe sizes. Reference Section 610.1, UPC 1994. 4. Include the static lift when performing the water pressure calculations. Reference Appendix A, UPC 1994. 5. Show how the fan-assisted flue for the water boiler was sized. Reference Section 103.2.3, UPC 1994 6. Provide upper terminal cleanouts on horizontal drainage pipes exceeding 5 feet in length (horizontal drain lines serving sinks and urinals require cleanouts regardless of length). Reference Section 707.4, UPC 1994. 7. Modify trap arm lengths to conform to Table 10-1, UPC 1994 with AZ State amendments. 8. Show the size of the runouts to the urinals and the water closets. Reference Section A6.1, UPC 1994. 9. Clarify the apparent disparity between the two boiler control and three pump circuits shown on electrical panels "S" and "P" and the plumbing design. |
06/28/2005 | ROBERT SHERRY | WATER | REVIEW | Approved | |
06/30/2005 | BOB SUBA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | 1.Provide a complete single line diagram showing all conduit and conductor sizes,transformers,grounding, and over current protection,fault current etc. |
07/15/2005 | RAUL PALMA | BUILDING-COMMERCIAL | REVIEW | Denied | . City of Tucson, Development Services BUILDING AND STRUCTURAL COMMENTS 1) Page 8c of the calcs under STEM CONSTRUCTION shows top stem and 2nd stem. Under top stem is shown 2 foot stem and under 2nd stem is shown 0' , but theheight of wall is supposed to be 8.67 ft. Clarify! |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
07/26/2005 | SUE REEVES | OUT TO CUSTOMER | Completed |
07/26/2005 | ANGIE SHOFFSTALL | REJECT SHELF | Completed |