Review Details: COMMERCIAL TI
Permit Number - T05CM02092
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/10/2005 | JIM EGAN | FIRE | REVIEW | Approved | |
05/10/2005 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Passed | |
05/10/2005 | RAUL PALMA | BUILDING-COMMERCIAL | REVIEW | Approved | |
05/10/2005 | ROBERT SHERRY | WATER | REVIEW | Approved | |
05/10/2005 | TERRY STEVENS | ZONING | REVIEW | Approved | |
05/10/2005 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Passed | |
05/10/2005 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | T05CM02092 DENIED 5/10/05 1. For the column totals on the panel schedule to be meaningful, they need to include existing loads. It shall be obvious that no phase is overloaded. 2. In the load calculations below the panel schedule, it appears that receptacles are 2340 VA, not 1980, and that fixed loads are 9105 VA not 8925. 3. Amps appear to be calculated wrong on load calculations below panel schedule. Even if 29218 VA were the correct figure, it would not be 35.1 A at 120/208. 4. Provide load calculations to show that Panel 15BB is not overloaded. 5. There is a new Water Heater on the Electrical Plans, but not Plumbing. Provide Plumbing plans. |
05/10/2005 | BLANCA ESPINO | ENGINEERING | REVIEW | Approved | |
05/12/2005 | EGRANT1 | WWM | REVIEW | Passed |