Review Status: Completed
Review Details: RESUBMITTAL - SITE ALL
Permit Number - T05CM02087
Review Name: RESUBMITTAL - SITE ALL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/16/2009 | TERRY STEVENS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Terry Stevens Lead Planner PROJECT: T05CM02087 5910 E. 5th St. Site Plan - Revision TRANSMITTAL DATE: 2/05/09 COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. DS 2-02.2.1.6 Provide on the site plan the dimensions of the foot prints of all structures. Add the special exception case number (T08SE00012) to the notes. 2. DS 2-02.2.2.A.3 The FAR calculations indicated in general note #5 have not been revised to show the changes to the plan. Revise. In general note number 4 the totals indicated are mixed up with the phase 2 totals. Revise. 3. Review DS 2-09 and provide a detail of an acceptable class 2 bicycle parking rack. Must have minimum 2 point support. Revise detail 7 on sheet 3. 4. The above comments are minor in nature and can be completed by setting an appointment with me for an over the counter review. If you have any questions about this transmittal, please call Terry Stevens, (520) 837-4961 C:\planning\cdrc\DSD\T05CM02087-rev.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents |
03/16/2009 | RONALD BROWN | ZONING HC SITE | REVIEW | Approved | |
03/17/2009 | ANDREW CONNOR | LANDSCAPE | REVIEW | Denied | 1. All disturbed, grubbed, graded, or bladed areas not otherwise improved shall be landscaped, reseeded, or treated with an inorganic or organic ground cover to help reduce dust pollution LUC 3.7.2.7 2. For any site one acre or greater or portion thereof which has been wholly or partially grubbed or wholly or partially graded, construction shall commence and shall be continuous within sixty (60) days after grubbing. Should construction or grading not commence or be continuous within the required sixty- (60) day period, the site shall be native seeded within thirty (30) days following the expiration of the required sixty (60) day period DS 11-01.2.3.A. Indicate if Phase 2 is to be left in a natural state or indicate treatment of exposed grubbed or grated area. |
03/18/2009 | ANDREW CONNOR | NPPO | REVIEW | Approved | |
04/06/2009 | PAUL MACHADO | ENGINEERING | REVIEW | Approved | |
04/09/2009 | DROBEY1 | PLUMBING-COMMERCIAL | REVIEW | Needs Review |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
04/09/2009 | DELMA ROBEY | APPROVAL SHELF | Completed |
04/09/2009 | DELMA ROBEY | OUT TO CUSTOMER | Completed |
04/09/2009 | DELMA ROBEY | REJECT SHELF | Completed |