07/06/2005 HEATHER THRALL ZONING REVIEW Denied DSD TRANSMITTAL

FROM: Heather Thrall Senior Planner FOR: David Rivera Principal Planner
PROJECT: T05CM01453
2651 E. Ganley Road
Commercial warehouse
Site plan
2nd Review
Transmittal date: July 8, 2005



COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

This plan was reviewed for compliance with sections 2-02 of the Development Standards. Other sections of the Development Standard and Land Use Code are referenced as applicable.

1. Please provide a note on the plan showing all handicapped ramps will not exceed a slope ratio of 1:12.

2. Truncated Domes (early warning systems) must be added to all access ramps where transitioning from the pedestrian area to the vehicular use area or at HC access aisles transitioning to the sidewalk area.

3. The pedestrian sidewalk to Ganley Road is shown covered with plants on the landscape plan. Please address this discrepancy, providing unimpeded pedestrian access to Ganley.

4. Please clarify if the concrete area noted as "29" on the site plan is flush with the adjacent access aisle or is a raised sidewalk.

5. Please demonstrate maneuverability into the loading zone proposed at the north end of the site. Note, all areas of vehicle use leading to the loading zone must be paved.

6. Per the AEZ/CUZ-2 overlay requirements, please note on the plan: "Per LUC 2.8.5.5.B.2, Structures or uses with fifty (50) or more employees must develop an emergency evacuation plan and training program and implement it as approved by the Fire Department". Please specify this project will comply with this requirement.

7.The lot split application, S04-187 per Development Services records, has not been finalized. The lot split must be finalized before staff can consider review of this project, as proposed. A copy of the city approved (lot split) site plan and associated lot split documents (i.e. address certificates from Pima County, legal descriptions and receipts recorded with the Pima County Recorder's Office, receipt showing the lot split application has been paid for) must be included with the revised site plan.

Should the lot split fail to proceed, the revised site plan should show the current lot boundaries. Updated floor area ratios and adjacent zoning information will then need to be provided for the proposed project.

8. If you have any questions on this review, please contact me at Heather.Thrall@tucsonaz.gov or at 520-791-4541x1156 to make an office appointment.


If you have any questions about this transmittal, please call (520) 791-5608.
07/08/2005 HEATHER THRALL ZONING HC SITE REVIEW Denied Please see zoning review comments.
07/12/2005 DOUG WILLIAMS ENGINEERING REVIEW Denied SUBJECT: Drainage Report and Site Review
DATE: 12 July 2005
ACTIVITY NUMBERS: T05CM01453
T15S, R14E, Section 8

Engineering Division has reviewed the resubmitted items, and may not recommend approval at this time. Please provide a revised site plan and a revised drainage report addressing the comments provided below. An over the counter review may be coordinated with me upon completion of these revisions. Please contact me to schedule an appointment if desired, at such time.

DRAINAGE REPORT:

1. The response to previous comment # 16 may not be accepted by this office. Recent Mayor and Council directive specifies that all new retention/detention basins must incorporate these items whenever possible. Please provide details and discussions of how the proposed detention/retention scheme will comply with landscaping, grading, and retention/detention technical design guidelines provided in Chapters 1 and 4 of the Pima County/City of Tucson Stormwater Retention/Detention Manual (DS 10-01.0), with particular attention/discussion given to how the basin will serve as a project amenity, a multi-use facility, serve for passive recreation, and how it will serve as a human activity zone, at a minimum.
2. Please revise the basin outlet weir dimension specified on Page 4, 2nd paragraph to match the dimension used/provided elsewhere in the report and on the site plan.
3. Please provide a copy of the site plan IN THE REPORT as an "exhibit" or "figure" in the report (previous comment # 4).

SITE PLAN:
The response and proposed design for 40' radius headers may not be approved as depicted. Right of way improvements may not extend (westward) beyond the west property line alignment, as is currently proposed. Please revise the plan accordingly (see redlines for possible alternatives).
Please submit a revised Drainage Report and Site Plan addressing the comments above, or call to schedule an appointment for review of the revised items.
I can be reached at 791-5550, ext.1189 or via email at Doug.williams@tucsonaz.gov

Doug Williams
Sr. Eng. Associate
Engineering Division
Development Services Department
07/15/2005 ANDREW CONNOR LANDSCAPE REVIEW Denied All improvements and site information shown on the landscape plan will be identical in size and location to those on site plan. Should revisions be required to plans, the same amendments will be made to the landscape plan, which will then be resubmitted along with the site plan per DS 2-07.2.1.A. Include any changes to the site plan on landscape plan such as basin reconfiguration or improvements.

Final Status

Task End Date Reviewer's Name Type of Review Description
07/19/2005 BETH GRANT OUT TO CUSTOMER Completed
07/19/2005 ANGIE SHOFFSTALL REJECT SHELF Completed