Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T05CM00311
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/25/2005 | JIM EGAN | FIRE | REVIEW | Denied | Exit corridor/exit separaton required for access to exits. |
01/25/2005 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Use the fixture unit values from Table 6-3 to determine the water piping sizes. Include all of the fixtures and the water requirements of the HVAC compnents. Reference Sections 610.1 and 610.5, UPC 1994. 2. Revise the size of the water pipes to correspond to the submitted water pressure calculations. 3. Revise the layout of the waste piping to show the fittings in the correct relationship to the direction of flow. Reference Section 311.7, UPC 1994. 4. Provide for a cleanout downstream of the lift station. |
01/25/2005 | MICHAEL ST. PAUL | ZONING | REVIEW | Approved | |
01/25/2005 | ROBERT SHERRY | WATER | REVIEW | Approved | |
01/25/2005 | BLANCA ESPINO | ENGINEERING | REVIEW | Approved | |
01/25/2005 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Provide ventilation calculations for the heating of the building. |
01/26/2005 | CHRISTY FOREMAN | BUILDING-COMMERCIAL | REVIEW | Needs Review | |
01/26/2005 | TACHONG1 | WWM | REVIEW | Needs Review | |
01/26/2005 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | t05cm00311 denied 1/26/05 1. Show Panel MP on plans. Could the panel marked MU indeed me MP? 2. EC-1 is specified on mechanical plans as 3/4 HP, but on panel schedule as 1 1/2 HP. Notes 2 and 4 on mechanical schedule appear to contradict one another. Coordinate with mechanical and recheck circuit loading per NEC Table 430.148. 3. Provide power requirements for EC-2 on mechanical plans. 4. Water heater is specified on plumbing. Could not find on electrical plans or schedules. 5. Smart pack and sign are on Panel Schedule P2. Could not find on plans. 6. Note that loading on panel P2 feder is close to ampacity of conductors and panel capacity. In fact, the high phase is over by a fraction of an amp. 7. Provide AFC and if necessary fault calculations to demonstrate proper rating of panels. 8. Provide size of Panel MP feeder. 9. P2 feeder Equipment Grounding Conductor shall be #4, not #6. Reference NEC Table 250.122. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
01/26/2005 | TAMI ACHONG | OUT TO CUSTOMER | Completed |