| 02/08/2006 | LOREN MAKUS | ENGINEERING | REVIEW | Denied | February 8, 2006 TO: Amco Enterprises, Inc. SUBJECT: Site Plan: Building Addition, 2420 N Jackrabbit Avenue REVIEWER: Loren Makus ACTIVITY NUMBER: T05CM05118 SUMMARY: The Site Plan and Grading Permit Application were reviewed by Development Services Department, Engineering Division on February 8, 2006. It was not approved. Please address the following comments. Site Plan Comments: 1. Delineate, label and dimension the sight visibility triangles for each driveway/PAAL location. (DS 2-02.2.1.A.10) For details on the sight visibility triangles reference Development Standard 3-01.5.0 The Grading plan will be approved after the site plan has been approved. Revise the Site Plan to address this comment and resubmit two copies for review. Include a letter explaining the comment has been addressed. If you have any questions or if you wish to discuss any of these comments, I can be reached at 520.791-5550 ext 1161 or by email at loren.makus@tucsonaz.gov. Loren Makus, E.I.T. Senior Engineering Associate Engineering Division Development Services |
| 02/21/2006 | ANDREW CONNOR | NPPO | REVIEW | Denied | Site plan approval is necessary to continue review. |
| 03/15/2006 | DAVID RIVERA | ZONING | REVIEW | Denied | 03/15/06 Development Services Department Zoning Review Section David Rivera Principal Planner Comments: As of this review date it does not appear that teh site plan and landscape plans havbe been approved. 1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the grading plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next grading plan submittal. 3. Zoning will re-review the grading plan on the next submittal to ensure compliance with the approved and stamped site plan. Additional comments may be forthcoming. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/28/2006 | ADRIANNE OLIVO | OUT TO CUSTOMER | Completed |