Permit Number: T05BU01178
Parcel: 12604022C

Review Status: Completed

Review Details: RESUBMITTAL - GRADING

Permit Number - T05BU01178
Review Name: RESUBMITTAL - GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/20/2005 ANDREW CONNOR NPPO REVIEW Approv-Cond
06/24/2005 BLANCA ESPINO ENGINEERING REVIEW Approved Grading Plan
1. As per FIRM Panel 2232K the Water Surface Elevation is 2495.50 (NGVD29) for the proposed structure, therefore the structure's Finished Floor Elevation is 2496.50 which will be set one foot above the WSE. Submit a map indicating footprints of proposed structures and FEMA's water surface elevations for comparison and clarification.

2. If using both datum's, add a note and indicate the datum shift foot difference.

3. Indicate a dimensioned cross section detail of PAAL from property line to property line. Identify and label all materials to be used.

4. Indicate a dimensioned cross section detail of housing area from property line to property line.

5. Indicate a dimensioned cross section detail of water-harvesting area. Indicate water surface elevation, top and bottom elevations of basin.

6. Sheet AS1.0, Key Note 30 indicates Roof spout or Scupper. Label all downspouts and sidewalk scuppers individually. Indicate a downspout and sidewalk scupper symbol in legend.

7. Sheet 2 of Paving and Grading Plan, identify and indicate a symbol in Legend for the following items; square symbol, arrows, bold dash lines, gray triangles, bold lines in sidewalk.

8. Sheet 2 of Paving and Grading Plan indicates an arrow crossing over the sidewalk area. All drainage is to be routed under sidewalks. Correct and revise.

9. Indicate a dimensioned cross section detail of wall on the northeast and southeast end of site. Demonstrate the acceptance of the natural flow and how it will not be obstructed.

10. Remove text that is crossed out, "5' SIDEWALK", "5' CURB OPENING".

11. Correct all text overlays.


Drainage Report
1. As per FIRM Panel 2232K the Water Surface Elevation is 2495.50 (NGVD29) for the proposed structure, therefore the structure's Finished Floor Elevation is 2496.50 which will be set one foot above the WSE. Submit a map indicating footprints of proposed structures and FEMA's water surface elevations for comparison and clarification.

2. If using both datum's, add a note and indicate the datum shift foot difference.


If you have any questions or would like to meet with me before your next submittal, you may contact me at 791-5640 ext.1188 or Blanca.Espino@tucsonaz.gov
06/28/2005 DAN CASTRO ZONING REVIEW Denied Zoning Review may not approve the grading plan prior to Engineering and Landscape approval.

Final Status

Task End Date Reviewer's Name Type of Review Description
07/05/2005 KMEDINA1 OUT TO CUSTOMER Completed