Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T05BU01145
Parcel: 14024073E

Review Status: Completed

Review Details: GRADING

Permit Number - T05BU01145
Review Name: GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/17/2005 ANDREW CONNOR NPPO REVIEW Denied Site plan approval is necessary to continue review.
06/06/2005 ELIZABETH EBERBACH ENGINEERING REVIEW Approved TO: George Holguin, RA
SUBJECT: Turbine Warehouse Engineering Review
Location: T15S, R14E, Section 7
ACTIVITY NUMBERS: T05BU01145 (Grading Plan review), T05CM00693 (Site Plan review)

SUMMARY: Engineering has received and reviewed the Grading Plan, Drainage Report, and for grading and site plan review. The grading plan is conditionally approved. The Building Official has stated in May 2005 that grading construction has already begun; this will incur the doubling of the grading permit fees. The drainage report was reviewed for grading purposes only.

GRADING/SITE PLAN CONDITIONS OF GRADING PERMIT:
1) TUCSON CODE SEC. 29-15(B)(1): APPLICANT MUST FILL OUT AND SIGN W.A.S.H. OVERLAY ZONE APPLICATION FORM PRIOR TO PICKING UP PERMIT. IF ANY DISTURBANCE OCCURS WITHIN THE W.A.S.H. ORDINANCE WASH AREA INCLUDING THE 50-FT STUDY AREA, A W.A.S.H. REPORT AND MITIGATION PLAN WILL BE REQUIRED TO BE SUBMITTED AND ACCEPTED PRIOR TO FINAL INSPECTION APPROVAL.
2) DEVELOPMENT STANDARDS (DS) SECTION 11-01.16.2: DSD ENGINEERING DIVISION INSPECTIONS ARE REQUIRED FOR INITIAL STORMWATER CONTROLS AS WELL AS GRADING PRE-CONSTRUCTION MEETING. FOR A DSD ENGINEERING INSPECTIONS, CALL IVR (740-6970), OR SCHEDULE WITH A CUSTOMER SERVICE REPRESENTATIVE AT THE DEVELOPMENT SERVICES DEPARTMENT, OR SCHEDULE INSPECTIONS ONLINE AT: HTTP://WWW.CI.TUCSON.AZ.US/DSD/ONLINE_SERVICES/ONLINE_PERMITS/ONLINE_PERMITS.HTML OR CONTACT DSD ENGINEERING AT 791-5550 EXTENSION 2101.
3) DS SEC.2-02.2.1.A.32: FOR REFUSE CONTAINERS, GATES OR DOORS FOR TRASH ENCLOSURES WILL BE REQUIRED AT INSPECTION.
4) ALL GRADING SHALL CONFORM TO DEVELOPMENT STANDARDS SECTION 11-01.
5) REGARDING LIMITS OF GRADING, A HEAVY DUTY CONSTRUCTION FENCE SHALL BE SET AT LEAST 50 FEET FROM TOP OF BANK OF AIRPORT WASH PRIOR TO FURTHER GRADING CONSTRUCTION AND INSPECTED AND ACCEPTED BY DSD ENGINEERING DIVISION GRADING INSPECTOR.
6) AT POST-GRADING CONSTRUCTION INSPECTION, ADDITIONAL PERCOLATION TESTING MAY BE REQUIRED.
7) THE STORMWATER POLLUTION PREVENTION PLAN (SWPPP) WILL BE REQUIRED IF AT ANY TIME IT IS DETERMINED THAT THE DISTURBANCE AREA EXCEEDS 1 ACRE.
8) ANY REVISION TO THE GRADING PLAN MAY REQUIRE A RE-SUBMITTAL OF THE REVISED GRADING PLAN FOR REVIEW. CONTACT DSD ENGINEERING AT 791-5550 TO DISCUSS CHANGES IN GRADING DESIGN.
9) IF GRADING CONSTRUCTION IS EXPECTED TO LAST LONGER THAN THE EXPIRATION DATE ON THE GRADING PERMIT, CONTACT DSD TO RENEW/EXTEND THE GRADING PERMIT. IF FINAL GRADING INSPECTION HAS NOT BEEN COMPLETED BEFORE THE GRADING PERMIT EXPIRES, AND THE PERMIT HAS NOT BEEN RENEWED, ADDITIONAL FEES AND REVIEWS MAY BE REQUIRED.
10) AS-BUILTS REQUIRED, WITH COMPLETION DOCUMENTATION (INCLUDING THE SUBSTANTIAL COMPLETION OF BASIN IN CONFORMANCE TO THE DRAINAGE REPORT AND PLANS) FROM PROJECT ENGINEER AT TIME OF FINAL GRADING INSPECTION.
11) A COPY OF THE GRADING PLAN, GRADING PERMIT, AND GEOTECHNICAL REPORTS SHALL BE KEPT AT THE SITE AT ALL TIMES, UNTIL FINAL GRADING APPROVAL.

For any questions, call me at 791-5550, extension 2204.

Elizabeth Eberbach, PE
Civil Engineer
Engineering Division
Development Services
06/15/2005 DAVID RIVERA ZONING REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
06/17/2005 CINDY AGUILAR OUT TO CUSTOMER Completed
06/17/2005 CINDY AGUILAR REJECT SHELF Completed