Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T05BU00480
Parcel: 141090210

Address:
7855 S WILMOT RD

Review Status: Completed

Review Details: RESUBMITTAL - GRADING

Permit Number - T05BU00480
Review Name: RESUBMITTAL - GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/09/2005 LAITH ALSHAMI ENGINEERING REVIEW Denied Laith Alshami, Engineering and Floodplain Review, 05/09/2005

The Stormwater Pollution Prevention Plan does not meet the minimum standards of the AzPDES Construction General Permit.

1. Part IV.C.2.b. Part IV.D.1. Part IV.D.2.a. Significant construction work is proposed for the drainageway through this project. Clearly describe the scheduling and other practices that will be followed to minimize erosion of the channel and banks while this construction is underway. Include these activities in the sequence of major activities. Describe the steps that will be taken when erosion occurs to prevent the sediment from migrating off site. Describe the steps that will be taken to clean up sediments that do accumulate off site.
2. Part IV.H.1. Describe the correct inspection schedule as required by the general permit. Inspections must be made every two weeks AND within 24 hours of a rain of a half inch or more, during the normally wet seasons of the year. During the dry seasons of the year, inspections must occur at least once a month, whenever rain is predicted AND within 24 hours after a rain of one half inch or more.

Include in the next submittal 3 copies of the SWPPP for the approval stamp.
05/20/2005 DAVID RIVERA ZONING REVIEW Denied 05/20/05

Development Services Department
Zoning Review Section

David Rivera
Principal Planner

Comments:

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the grading plan was in compliance with the approved site plan or development plan. Please submit copies of the CDRC approved and stamped tentative plat, landscape, and NPPO plans with the next grading plan submittal.

3. Zoning will re-review the grading plan on the next submittal to insure compliance with the CDRC approved and stamped tentative plat and Landscape and NPPO. Additional comments may be forthcoming.
05/25/2005 ANDREW CONNOR NPPO REVIEW Denied Submit approved tentative plat including landscape and NPP plans to continue review.

Final Status

Task End Date Reviewer's Name Type of Review Description
05/31/2005 KMEDINA1 OUT TO CUSTOMER Completed
05/31/2005 SUE REEVES REJECT SHELF Completed