Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T04CM05480
Parcel: 12905130L

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T04CM05480
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/01/2005 PETER MCLAUGHLIN ZONING REVIEW Denied Approved site plan required prior to building plan approval.
06/07/2005 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied Comment not addressed. Show how the heat lamps that are being used to provide heat for the restrooms are being controlled. Reference Section 309.1, IMC 2000.
06/07/2005 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Comment not addressed. Resize the reduced pressure backflow preventor to comply to Section 610.2, UPC 1994.
2. Third request. Provide equipment data (e.g. electrical data and operation of the immersion heaters) for the water heater. Reference Section 103.2.3, UPC 1994.
3. Comment not addressed. The location of the expansion tank for the water heater, as shown on the plans, is incorrect. Revise the installation to comply with the manufacturer's listing requirements. Reference Section 608.3, UPC 1994 with AZ State amendments.
4. Comment not addressed. Revise the water pressure calculations to include the actual minimum main supply pressure (available from Tucson Water) and the head losses (pressure drop due to the water meter, reduced pressure backflow preventer and the static lift). Reference Sections 610.2, 610.7, and 610.8, UPC 1994. Note also that the water meter is too small for the proposed installation. Resize the water pipe sizing as required.
5. Comment not addressed. Revise the calculation of the total demand by using 5 fixture units per hose bibb. There is no discount for multiple hose bibbs in Tables 6-3 or A-2 of the 1994 edition of the UPC. Reference Sections 610.1 and 610.3, UPC 1994.
6. Comment not addressed. Clarify how access is being provided to the water heaters. The notes on sheets A2 and A3 appear to show the steel studs of the restroom walls extending to the structure.
06/17/2005 CHRISTY FOREMAN BUILDING-COMMERCIAL REVIEW Denied 1) Approval of site plan needs to be issued by zoning before structural plans examiner can approve to verify changes made for zoning do not affect accessibilty to building.

Final Status

Task End Date Reviewer's Name Type of Review Description
06/24/2005 KMEDINA1 OUT TO CUSTOMER Completed