Permit Review Detail
Review Status: Completed
Review Details: SITE
Permit Number - T04CM04312
Review Name: SITE
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/06/2004 | Jim Egan | FIRE | REVIEW | Approved | |
| 10/12/2004 | Andrew Connor | LANDSCAPE | REVIEW | Denied | Indicate on site plan both the proper and common name of each type of plant material per DS 2-07.2.2.A.1.d Submit application for exception, which clearly indicates that the project will not impact Protected Native Plants per DS 2-15.2.0 |
| 10/13/2004 | ANDREW CONNOR | NPPO | REVIEW | Denied | Indicate on site plan both the proper and common name of each type of plant material per DS 2-07.2.2.A.1.d Submit application for exception, which clearly indicates that the project will not impact Protected Native Plants per DS 2-15.2.0 |
| 10/20/2004 | Daniel Castro | ZONING | REVIEW | Denied | 1. Provide a copy of the last approved site plan for the park. The copy of the last approved site plan attached to the proposed plans is for a diffrent location. 2. The site is zoned I-1, which does not all the "Neighborhood Recreation" land use. An Administrative Waiver may be required if the site has yet to be approved for a park. 3. Additional comments may be forthcoming upon resubmittal of this plan. |
| 10/21/2004 | DAN CASTRO | HANDICAP-SITE | REVIEW | Passed | |
| 10/29/2004 | Loren Makus | ENGINEERING | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 11/03/2004 | TAMI ACHONG | OUT TO CUSTOMER | Completed |
| 11/03/2004 | SUE REEVES | REJECT SHELF | Completed |