Permit Number: T04CM03815
Parcel: 11449030A

Review Status: Completed

Review Details: POST 3RD PARTY REVIEW

Permit Number - T04CM03815
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/07/2004 ROBERT SHERRY WATER REVIEW Approved
10/07/2004 JIM EGAN FIRE REVIEW Approved
10/14/2004 PAUL MACHADO ENGINEERING REVIEW Approved
10/21/2004 SEPTIC APPROVAL WWM REVIEW Approv-Cond DEQ- Septic approved under P04CP07057. NO OCCUPANCY UNTIL SYSTEM HAS BEEN INSTALLED AND APPROVED.
Bob Flynt 740-6502
10/21/2004 DAVID RIVERA ZONING REVIEW Denied October 19, 2004

Development Services Department
Zoning Review Section

David Rivera
Senior Planner

Comments:

1. The building plans cannot be approved at this time. Development plan is under review by CDRC staff and has not been approved. The building plans cannot be approved until the development plan, landscape plan, and NPPO plan have been approved.

2. Two copies of the approved and stamped development/site plan, landscape and NPPO plans must be included with grading plan.

3. A site card with DSD approvals by Fire, Zoning, Handi-cap, Engineering, and Landscape/NPPO including the approved development plan stamped for site plan approval and signatures is required before the grading plan can be approved by Zoning. Two copies of the approved development plan, landscape and NPPO plans are to be submitted with the grading plans packet for processing and approval as a site plan. No fees are involved in re-stamping the development/tentative plat plans as an approved site plan. The development plan, may be walked through for stamps and site card sign off. submit the following: two copies of the stamped development plan, landscape and NPPO plans must be included with the building plans packet processed together for site approval.

4. Zoning will re-review the building plans on the next submittal with the approved development plan stamped as a site plan.

Final Status

Task End Date Reviewer's Name Type of Review Description
12/16/2004 DELMA ROBEY OUT TO CUSTOMER Completed