Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T04CM03681
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/16/2004 | Paul Machado | ENGINEERING | REVIEW | Approved | |
09/17/2004 | Jim Egan | FIRE | REVIEW | Denied | PROVIDE FIRE SPRINKLER SYSTEM DESIGN CRITERIA ON PLAN. |
09/23/2004 | Daniel Castro | ZONING | REVIEW | Denied | Building plans submitted for review do not match the approved development plan case number D03-0023. Building sizes and footprints have changed. Prior to the approval of the building plans by the Zoning Review Section the following must occur: Three copies of the revised development plan sheets 1 and 2 are required to be submitted for Zoning and Engineering Review. Revised development plan sheets 1 and 2 must provide all revised information (i.e. floor area ratio, parking, loading calculation). The 3 sets must be submitted to the Zoning Review Section and the review period is usually 5 working days. Once the revised development plan is approved the building plans may then be approved by Zoning Review. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
09/27/2004 | TAMI ACHONG | OUT TO CUSTOMER | Completed |
09/27/2004 | ANGIE SHOFFSTALL | REJECT SHELF | Completed |