Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T04CM03013
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/04/2006 | JOSE ORTIZ | ENGINEERING | REVIEW | Denied | A stamped approved Site Plan required prior to approval. |
| 05/10/2006 | RAUL PALMA | BUILDING-COMMERCIAL | REVIEW | Denied | City of Tucson, Development Services BUILDING AND STRUCTURAL COMMENTS 1) Include the existing building in the lateral design for wind and seismic, if structure is physically attached to the new structure. If not physically attached then existing structure does not have to be included in the lateral design. 2) Provide a footing design. 3) Sheets 4 and 5 of calcs shows the lateral load as 15 psf but on sheet 3 it is shown as 16.5 psf. Also, the STRUCTURE DESIGN CRITERIA sheet shows it as 16.5psf. CLARIFY! 4) Sheet 7 of calcs, specify the size of bolts, lumber grade and species, size of ledger and perpendiculer or parallel to the grain, specify the value used. 5) Sheet 8 of calcs, where was the value of 1330 obtained? Provide reference. 6) Provide smoke detectors in sleeping rooms. done 7) State on plans"window sill shall be limited to a max of 44 inches from the finished Floor." done 5/10/06 1) Provide responses for comments 1,2,3,4, and 5, of comments above. |
| 05/16/2006 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL. PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov IF YOU CARE TO DISCUSS. 1. Seal, sign, and date Sheet A-2. Reference Arizona Revised Statute ยง 32-125. 2. Provide Ground-Fault Circuit Interrupter Protection for exterior and countertop receptacles (Apt 1). Reference NEC 210.8. THIS COMMENT WAS MADE ON THE PREVIOUS TWO SUBMITTALS. 3. Load calculations, as presented, appear to tally 11,845 VA, not 11,095 VA. With the addition of the EFs and the Indoor Unit on the Split system, the total appears to be 12909 VA. Please correct this to give the Owner a better sense of spare capacity. 4. Correct the terminology "AIC FAULT CURRENT INTERRUPTION" to read "ARC-FAULT CIRCUIT-INTERRUPTER PROTECTION." 5. Applicant shall go to Pima County Addressing to obtain addresses for all new/relocated meters. Take such addresses to DSD Permit Clerks for data entry into the City permitting system. Addresses for all new meters as shown on the plans shall correspond to those in City/County database. |
| 05/19/2006 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Approved | |
| 05/24/2006 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Second request. Revise the waste and vent riser diagram to include all of the pipe sizes and coordinate the diagram with the plumbing plan. Reference Section 103.2.3, UPC 2003. Where does the 4" building drain start? If it starts downstream of the lavatory, provide a cleanout sized per Table 7-6 for the 4" building drain. Show the location of the cleanout (shown near the kitchen sink on the plumbing plan) on the soil riser diagram. Revise the connection of the waste from the kitchen sink and the building drain per Section 311.7, UPC 2003. Coordinate the vents shown on the soil riser diagram and the vents noted on the plumbing plan. The new waste piping for apartment #3 is not shown in a riser diagram but is shown without vents on the plumbing plan. 2. Comments not addressed. Provide cleanouts in the building sewer at intervals not exceeding 100 feet. Reference Section 719.1, UPC 2003. Show the location of the cleanouts on the site plan. 3. Third request. Provide equipment data for the water heater. Reference Section 103.2.3, UPC 2003. Note that the note on detail 2/MP-1 that the "water heater spec to comply with UPC 1994, Section 103.2.3 4. Second request. If the furnace is installed in apartment #3, provide adequate maintenance access to the water heater. Reference Section 310.4, UPC 2003. Note that sheet A-2 also shows an existing electrical panel being blocked by the installation of the water heater. |
| 06/03/2006 | DAVID RIVERA | ZONING | REVIEW | Denied | June 3, 2006 Development Services Department Zoning Review Section David Rivera Principal Planner Comments 1. Zoning has reviewd the building plans but cannot approve plans until the site plan has been approved. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 06/09/2006 | ADRIANNE OLIVO | OUT TO CUSTOMER | Completed |
| 06/09/2006 | SUE REEVES | REJECT SHELF | Completed |