| 06/09/2004 | Jim Egan | FIRE | REVIEW | Denied | 1. Minimum 18' turn radii required at 6 locations. 2. Fire hydrant required.(Show correct locations for existing fire hydrants.) |
| 06/09/2004 | Joseph Linville | LANDSCAPE | REVIEW | Approved | |
| 06/11/2004 | JOE LINVILLE | NPPO | REVIEW | Denied | Submit set-aside documentation for Starr Pass. Revise the NPP plans to include limits of grading/disturbance. Fencing will be required at the limits of disturbance. |
| 06/14/2004 | David Rivera | ZONING | REVIEW | Denied | COMMENTS: Please attach a response letter with the next submittal, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. (CODE SECTION/ DEVELOPMENT STANDARD) 1. Since a new lot is being created, a lot split application review will be required. A copy of the lot split application and instructions may be obtained by contacting me at the number provided below or at the Zoning counter. Lot split approval is required prior to site plan approval. (D.S. 2-02.2.1.A.2) (LUC 4.3.1) 2. Correct the building setback requirements noted on the site plan and listed under Code Review sheet A1 to be based on the proposed building height of 21 feet. (D.S. 2-02.2.1.A.7) 3. Lot Development Option (LDO) approval is required for the building setbacks which do not comply with zoning requirements. Add the following information as a general note: LDO case number, date of approval, setback modifications granted, and any conditions imposed. LDO must be approved prior to site plan approval. (D.S. 2-02.2.1.A.7) 4. Dimension the width of the standard vehicle parking spaces. (D.S. 2-02.2.1.A.8) 5. Detail access ramps. Ramps must be in conformance with ICC/ANSI A117.1-1998 Section 405. (D.S. 2-02.2.1.A.8) 6. Provide the bicycle parking calculation. If parking is to be provided, provide a fully dimensioned bicycle parking space detail and indicate the location/s on the plan. (D.S. 2-02.2.1.A.9) (D.S. 2-09) (LUC 3.3.4) 7. Provide a vehicle and pedestrian cross access agreement. The agreement must be recorded prior to site plan approval and a copy submitted to the Zoning Review Section for DSD records. If you have any questions about this transmittal, please call Dan Castro, (520) 791-5608. |
| 06/15/2004 | DAN CASTRO | HANDICAP-SITE | REVIEW | Denied | Detail access ramps. Ramps must be in conformance with ICC/ANSI A117.1-1998 Section 405. (D.S. 2-02.2.1.A.8) |
| 06/16/2004 | MATT FLICK | ENGINEERING | REVIEW | Denied | Engineering Comments for T04CM02573 Site Plan: Indicate location of bank protection key-in near southwestern point of garage. Indicate location, size and type of scupper to be installed beneath sidewalk along northwester face of garage. Bank protection is shown along parking area that is not indicated in drainage report. Resolve discrepancy. Realign dumpster approach to provide 40' clear approach per DS 6-01.4.1.C. Provide dumpster pad and enclosure meeting requirements of DS 6-01.4.1. Show details on plan. Landscape Plan: Indicate location of bank protection key-in near southwestern point of garage. Relocate tree out of sidewalk along northwestern face of garage |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 06/16/2004 | LISA LESNY | OUT TO CUSTOMER | Completed |