Permit Review Detail
Review Status: Completed
Review Details: REVISION - SITE
Permit Number - T04CM02462
Review Name: REVISION - SITE
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/16/2005 | JIM EGAN | FIRE | REVIEW | Approved | |
| 03/30/2005 | ANDREW CONNOR | NPPO | REVIEW | Passed | Exception previously approved. |
| 03/30/2005 | MICHAEL ST. PAUL | ZONING | REVIEW | Denied | Please print this in monochrome, no half-tones. |
| 03/31/2005 | ANDREW CONNOR | LANDSCAPE | REVIEW | Denied | Submit previously approved landscape plans to continue review. |
| 04/08/2005 | JORTIZ3 | ENGINEERING | REVIEW | Denied | DATE: April 8, 2005 ACTIVITY NUMBER: T04CM02462-R PROJECT ADDRESS: 350 W. Delano St PROJECT REVIEWER: Jose Ortiz, P.E. The following items must be revised or added to the site plan. Please include a response letter with the next submittal that states how all comments have been addressed. Resubmittal Required: Modified Hydrology Report, possibly a Flood Use Permit Application, possibly a Grading Plan General Comments The applicant must resubmit the original Hydrology Report with proper modifications providing information on the effects that units 5 & 6 have on existing drainage conditions. The Hydrology Report will be reviewed for site plan, grading plan and floodplain permit purposes. Site Plan and Grading Plan Comments 1. Units 5 and 6 are being added to a location labeled for "No Disturbance" on the approved plans. Therefore due to the fact that this area will most likely need grading the applicant will be required to verify whether a grading permit is required. 2. If the grading for units 5 & 6 exceeds 50 CY then a grading plan will be required. The grading information on the submitted grading sheet is unclear and it appears that the information from the older submittal was copied over. How much grading is involved with the proposed construction of units 5 & 6? 3. Need to seek approval by Jack Clark for the location of the solid waste facility. The solid waste collection area appears to be in a position that will not allow sanitation vehicles the proper mobility to access the bin. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 04/11/2005 | GBONILL1 | OUT TO CUSTOMER | Completed |
| 04/11/2005 | SUE REEVES | REJECT SHELF | Completed |