Permit Number: T04CM02255
Parcel: 121016260

Review Status: Completed

Review Details: COMMERCIAL TI

Permit Number - T04CM02255
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/20/2004 PATRICIA GILBERT ENGINEERING REVIEW Needs Review
05/20/2004 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Provide pressure regulator for water service. Reference Section 608.2, UPC 1994.
2. Revise the water pressure calculations using the reduced water pressure and use Table 6-4 to resize the pipes. Reference Sections 610.4 and 608.2, UPC 1994.
3. Revise the waste fixture units for the 2-compartment sink to match the value shown in Table 7-3, UPC 1994.
4. Include the water outlet for the icemaker in the fixture unit calculations. Reference Section 610.1, UPC 1994.
05/20/2004 ROBERT SHERRY WATER REVIEW Approved
05/20/2004 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Approved
05/21/2004 JIM EGAN FIRE REVIEW Approved
05/25/2004 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied T04CM02255 DENIED 5/25/04
1. Please account for the load on Ckt A-29, as five receptacles.
2. Please note that sing lighting circuits required in NEC 600-5 (a) shall be counted at 1200 VA.
3. Please note that Phase A totals 16704 VA, not 11844.
4. Phase B totals 15940, not 13934.
5. Phase C totals 13072 not 13404.
6. Per the above amps should read 139A, not 116.
7. Lighting loads appear to total 7362 VA at 125%, not 5134.
8. General receptacle loads appear tot total 5940 VA, not 4500.
9. Fixed loads appear to total 12000 VA, not 10725.
10. Largest motor load at 125% appears to total 13612, not 7200.
11. Remaining mechanical loads appear to total 10996 VA, not 12940.
12. On the basis of the above total appears to be 49710, not 40499 VA.
13. On the basis of the above, amps should read 138, not 112.4.
14. Please make the appropriate corrections per all of the above comments, and reflect such corrections in Details 4 & 5.
15. On Detail 2, provide size for the CB on Keynote 6.
16. On the panel schedule, please clarify 120/240. It appears that this is 120/208.
06/04/2004 EGRANT1 WWM REVIEW Needs Review
06/04/2004 EGRANT1 ZONING REVIEW Needs Review
06/04/2004 EGRANT1 BUILDING-COMMERCIAL REVIEW Needs Review