Permit Number: T04CM01533
Parcel: 11003093A

Review Status: Completed

Review Details: COMMERCIAL TI

Permit Number - T04CM01533
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/05/2004 Jim Egan FIRE REVIEW Approved
04/05/2004 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Recalculate pressure loss calculations and resize pipe in accordance with Sections 610.5 and 610.6, UPC 1994. Include the pressure drops associated with the water meter and the reduced pressure backflow preventer in the calculation of the available static pressure prior to using Table 6-4.
2. Provide rim elevation of next upstream sanitary manhole and first floor elevation. Determine need for backwater valve per Section 710.1, UPC 1994.
3. Show the routing of the building sewer and any cleanouts for the building sewer. Reference Section 103.2.3, UPC 1994.
04/05/2004 ROBERT SHERRY WATER REVIEW Approved
04/05/2004 Robert Sherry MECHANICAL-COMMERCIAL REVIEW Approved
04/16/2004 Martin Haeberle BUILDING-COMMERCIAL REVIEW Denied 1. Revise data sheet to reflect one restroom required per section 2902.2 IBC.
2. Occupant load to reflect Table 1003.2.2.2 IBC. Revise to 8
3. Water closet working clearance to be 60 inches. Lavatory not allowed to encroach into this area. Reference section 604.3 ANSI A117.1
4. Revise allowable area to reflect IBC table 503 IBC.
5. Provide lighted exit signs per section 1003.2.11 IBC
04/19/2004 GERRY KOZIOL WWM REVIEW Approved
04/20/2004 PATRICIA GEHLEN ZONING REVIEW Denied Zoning
4/20/2004
Building plans may not be reviewed and approved until the site plan is approved.
04/22/2004 Linda Buczynski ELECTRICAL-COMMERCIAL REVIEW Denied TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1106 OR EMAIL AT LBUCZYN1@CI.TUCSON.AZ.US
IF YOU CARE TO DISCUSS.

1. WH-1 is 3 KW, 2081/60, 14.4 A on Sheet P-1. On the electrical plans the water heater is 2.4 KW, 120/1/60, which means 20A. Please clarify.
2. All exterior lighting fixtures shall be listed for wet locations.
3. Provide catalogue cut sheets for the 150W flood light. Note that this fixture shall have full cutoff lighting distribution per the Outdoor Lighting Ordinance.
4. Load calculations indicate 72 A. This is incorrect per the panel schedule. Please clarify.
5. Provide power for lighted exit sighs per Structural Comments.
04/29/2004 PAUL MACHADO ENGINEERING REVIEW Denied A copy of the stamped approved Site Plan must be included in the submittal.

Final Status

Task End Date Reviewer's Name Type of Review Description
05/03/2004 EGRANT1 OUT TO CUSTOMER Completed
05/03/2004 EGRANT1 REJECT SHELF Completed