Permit Review Detail
Review Status: Completed
Review Details: REVISION
Permit Number - T04CM00999
Review Name: REVISION
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/30/2004 | Joseph Linville | LANDSCAPE | REVIEW | Denied | 1) Submit copies of the site plans approved for zoning compliance including landscape and native plant preservation plans. Revise all plans as necessary and submit revised documents. |
| 08/03/2004 | BLANCA ESPINO | ENGINEERING | REVIEW | Approv-Cond | Indicate DSMR#, approval date and conditions on Site Plan. |
| 08/16/2004 | David Rivera | ZONING | REVIEW | Denied | August 17, 2004 Development Services Department Zoning Review Section David Rivera Senior Planner Comments: 1. The revised site plan has been reviewed by the Zoning Review Section but cannot approve the plan until it has been approved by the Landscape Review Section and approval of the revised site plan. 2. a copy of the previously approved and stamped site plan, landscape, NPPO and grading plans must be included with revised site plan. If the changes are minor I will review and approve both the site plan and grading plan over the counter but you must ask the landsdcape reviewer if they are willing to do the same otherwise the plans must be re-submitted for review and approval. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 08/18/2004 | BETH GRANT | OUT TO CUSTOMER | Completed |
| 08/18/2004 | SUE REEVES | REJECT SHELF | Completed |