Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T04CM00990
Parcel: 132166160

Review Status: Completed

Review Details: COMMERCIAL TI

Permit Number - T04CM00990
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/02/2004 BLANCA ESPINO ENGINEERING REVIEW Approved
03/02/2004 PETER MCLAUGHLIN ZONING REVIEW Approved
03/03/2004 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Passed
03/03/2004 JIM EGAN FIRE REVIEW Approved
03/03/2004 ROBERT SHERRY WATER REVIEW Approved
03/03/2004 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied Show size, route, and termination of the condensate drain from HP-1.
03/09/2004 MARTIN HAEBERLE BUILDING-COMMERCIAL REVIEW Denied
03/09/2004 CAGUILA1 WWM REVIEW Passed
03/09/2004 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied T04CM00990 DENIED 3/9/04
Need second page of second set to obtain approval on walk-through.

T04CM00990 DENIED 3/3/04
1. There are branch circuits on Panel 105B. There are only panel schedules for panels 105A and 105. Please clarify and make nomenclature consistent on plan views, panel schedules, and line diagram.
2. Phase C on panel labeled "105" appears to have 7065 VA, not 5145. Please clarify, and carry through load calculations.
3. New transformers are 30 KVA on single line diagram, and 45 KVA on panel schedules. Please clarify.
4. Load on Panel 103B of 70A, when transformed to 480V, would be about 34A. If so, a 20A CB is not adequate.
5. #8 has ampacity of 50A, and therefore the 60A CB on Circuit 105A-8,10,12 does not protect the conductor at its ampacity.
6. Fault calculations for Faults #2 and #3 use 3 conductors in parallel. There are 3/0 conductors, one set each, in these conduit runs. Please clarify.