Permit Number: T04CM00686
Parcel: 103090670

Review Status: Completed

Review Details: 3RD PARTY REVIEW-COMMERCIAL

Permit Number - T04CM00686
Review Name: 3RD PARTY REVIEW-COMMERCIAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/20/2004 SREEVES1 WWM REVIEW Needs Review
02/20/2004 SREEVES1 ENGINEERING REVIEW Needs Review
02/20/2004 SREEVES1 3RD PARTY REVIEW-COMMERCIAL REVIEW Denied SEVERAL PAGES OF COMMENTS
The initial review for the above project has been completed. This letter reflects comments which need to be addressed by a written response to each, indicating action taken. In order to facilitate a shorter back-check time, we request that you please provide two (2) sets revised plans and calculations, highlighting any changes with appropriate revision number, revision date, and “cloud bubbles.” Please replace all revised drawing sheets, in all sets of plans, before returning to Willdan for the follow-up plan review. Please return redline drawings with your resubmittal.


Occupancy
Occup. Load
Construction
Area S.F.
Sprinklered
Alarms

A-3
1,023
V-B
11.180
Yes
Yes


GENERAL COMMENTS:

This project has been reviewed for conformance with the 2000 IBC, 1997 UAC, 2000 IMC, 1998 IECC, 1999 NEC codes with local modifications, and the 1994 UPC with State of Arizona Amendments. Any revisions to this plan will require an additional review and approval by Willdan.


ARCHITECTURAL COMMENTS:

Sheet T.1

It appears the gross square footage of the structure has been incorrectly identified. Please review and correct as necessary. Reference IBC Section 106.1.1.

It appears information for more than one project has been incorporated into this set of drawings. There is a reference to BUILDING “D” which contains information for a small amount of demolition work and HVAC upgrade. This work will require a separate permit and additional information related to the demolition of the identified interior partitions. Reference IBC Section 106.1.1.

Sheet A1.1

Please provide a section through the platforms demonstrating compliance with the provisions ADAAG for access and 1003.3.3.3 for stairs. Reference ADAAG Section 4.1.6 and IBC Section 1003.3.3.3.

Please provide details for the bracing of all walls that do not extend to the existing roof structure above. Reference IBC Section 106.1.1.

Please clarify the door hardware for Doors 101A, 101B, 101C, 108A, and 111A. Coordinate this information with the Door Schedule on Sheet A2.1. Reference IBC Section 1003.3.1.9.

Please clarify the keynote *** that is indicated at the seating in the sanctuary. Additionally, provide an exploited view of the seating demonstrating the clearance requirements for the fixed seating. Reference IBC Sections 106.1.1, 1008.8, and 1008.9.

Sheet A2.1

See Comment 3 above.

Sheet A3.2

Provide additional exits signs as redlined, Door 101A and 108A. Coordinate the reflected ceiling plan with Sheet E5. Reference IBC Section 1003.2.10.


STRUCTURAL COMMENTS:

Sheet A3.2

Provide a bracing detail for the installation of the T-Bar ceiling. Reference IBC Section 803.8.1.1.


PLUMBING COMMENTS:

Sheet P1.2

Note that the required size of the venting system shall be equal to the minimum required size of the building drain. Increase the size of the 3” vent at the main trunk or increase the size of the 2” vent at the secondary trunk. Reference UPC Table 704 and UPC Section 904.1.


MECHANICAL COMMENTS:

Sheet M1.1

It appears information for more than one project has been incorporated into this set of drawings. There is a reference to BUILDING “D” which contains information for a small amount of demolition work and HVAC upgrade. This work will require a separate permit and additional information related to the demolition of the identified interior partitions. Reference IBC Section 106.1.1.

Sheet M2.2

Please provide additional information for the referenced rooftop condensate receiver. Reference IMC Sections 106.3.1 and 307.


ELECTRICAL COMMENTS:

Sheet E4

Note that the identified location of the drinking fountains is different than that shown on the architectural floor plan. Coordinate the location of the fountains and the associated electrical outlets. Reference IBC Section 106.1.1.

Please provide exterior exit illuminations at all exits from the building. Reference IBC Sections 1003.2.11.2 and 1003.2.11.3.

Sheet E5

Provide additional exits signs as redlined, Doors 101A, 101B, 101C, 105B, 111A, 112B, and 114B. Coordinate with the reflected ceiling plan. Reference IBC Section 1003.2.10.

An exit sign at the Northwest corner of the sanctuary appears to be misplaced. Please clarify. Reference IBC Section 106.1.1.


ENERGY CODE COMMENTS:

Sheet E5

Please provide lighting controls in Rooms 112, 113, and 114 that will permit the lighting to be controlled as required by IECC Section 705.2.1.

Sheet E6

Provide the lighting load calculation for the building demonstrating compliance with IECC Section 705.4 and Table 705.4.

It does not appear the load from electrical panel 114 has been calculated into the total load calculation. Additionally, there does not appear to be a Panel Schedule for Panel 114 or FHP. Please clarify. Reference IBC Section 106.1.1.


ACCESSIBILITY COMMENTS:

Sheet A1.1

Please provide a section through the platforms demonstrating compliance with the provisions ADAAG for access and 1003.3.3.3 for stairs. Reference ADAAG Section 4.1.6 and IBC Section 1003.3.3.3.

Please confirm the latch side/push side clearances for Doors 101G and 101F for conformance with the provisions of ADAAG Figure 4.13.6.

It does not appear that provision have been made to accommodate wheelchair accessibility for participation in facility services. Please clarify. Reference ADAAG Section 4.32.

Please identify the accessible route from the building to the accessible parking facilities and the public way. Reference ADAAG Section 4.6.
02/20/2004 SREEVES1 ZONING REVIEW Needs Review
02/20/2004 SREEVES1 WATER REVIEW Needs Review
02/20/2004 JIM EGAN FIRE REVIEW Approved
02/20/2004 SREEVES1 3RD PARTY REVIEW-COMMERCIAL AT 3RD PARTY OFFICE Completed SEVERAL PAGES OF COMMENTS
The initial review for the above project has been completed. This letter reflects comments which need to be addressed by a written response to each, indicating action taken. In order to facilitate a shorter back-check time, we request that you please provide two (2) sets revised plans and calculations, highlighting any changes with appropriate revision number, revision date, and “cloud bubbles.” Please replace all revised drawing sheets, in all sets of plans, before returning to Willdan for the follow-up plan review. Please return redline drawings with your resubmittal.


Occupancy
Occup. Load
Construction
Area S.F.
Sprinklered
Alarms

A-3
1,023
V-B
11.180
Yes
Yes


GENERAL COMMENTS:

This project has been reviewed for conformance with the 2000 IBC, 1997 UAC, 2000 IMC, 1998 IECC, 1999 NEC codes with local modifications, and the 1994 UPC with State of Arizona Amendments. Any revisions to this plan will require an additional review and approval by Willdan.


ARCHITECTURAL COMMENTS:

Sheet T.1

It appears the gross square footage of the structure has been incorrectly identified. Please review and correct as necessary. Reference IBC Section 106.1.1.

It appears information for more than one project has been incorporated into this set of drawings. There is a reference to BUILDING “D” which contains information for a small amount of demolition work and HVAC upgrade. This work will require a separate permit and additional information related to the demolition of the identified interior partitions. Reference IBC Section 106.1.1.

Sheet A1.1

Please provide a section through the platforms demonstrating compliance with the provisions ADAAG for access and 1003.3.3.3 for stairs. Reference ADAAG Section 4.1.6 and IBC Section 1003.3.3.3.

Please provide details for the bracing of all walls that do not extend to the existing roof structure above. Reference IBC Section 106.1.1.

Please clarify the door hardware for Doors 101A, 101B, 101C, 108A, and 111A. Coordinate this information with the Door Schedule on Sheet A2.1. Reference IBC Section 1003.3.1.9.

Please clarify the keynote *** that is indicated at the seating in the sanctuary. Additionally, provide an exploited view of the seating demonstrating the clearance requirements for the fixed seating. Reference IBC Sections 106.1.1, 1008.8, and 1008.9.

Sheet A2.1

See Comment 3 above.

Sheet A3.2

Provide additional exits signs as redlined, Door 101A and 108A. Coordinate the reflected ceiling plan with Sheet E5. Reference IBC Section 1003.2.10.


STRUCTURAL COMMENTS:

Sheet A3.2

Provide a bracing detail for the installation of the T-Bar ceiling. Reference IBC Section 803.8.1.1.


PLUMBING COMMENTS:

Sheet P1.2

Note that the required size of the venting system shall be equal to the minimum required size of the building drain. Increase the size of the 3” vent at the main trunk or increase the size of the 2” vent at the secondary trunk. Reference UPC Table 704 and UPC Section 904.1.


MECHANICAL COMMENTS:

Sheet M1.1

It appears information for more than one project has been incorporated into this set of drawings. There is a reference to BUILDING “D” which contains information for a small amount of demolition work and HVAC upgrade. This work will require a separate permit and additional information related to the demolition of the identified interior partitions. Reference IBC Section 106.1.1.

Sheet M2.2

Please provide additional information for the referenced rooftop condensate receiver. Reference IMC Sections 106.3.1 and 307.


ELECTRICAL COMMENTS:

Sheet E4

Note that the identified location of the drinking fountains is different than that shown on the architectural floor plan. Coordinate the location of the fountains and the associated electrical outlets. Reference IBC Section 106.1.1.

Please provide exterior exit illuminations at all exits from the building. Reference IBC Sections 1003.2.11.2 and 1003.2.11.3.

Sheet E5

Provide additional exits signs as redlined, Doors 101A, 101B, 101C, 105B, 111A, 112B, and 114B. Coordinate with the reflected ceiling plan. Reference IBC Section 1003.2.10.

An exit sign at the Northwest corner of the sanctuary appears to be misplaced. Please clarify. Reference IBC Section 106.1.1.


ENERGY CODE COMMENTS:

Sheet E5

Please provide lighting controls in Rooms 112, 113, and 114 that will permit the lighting to be controlled as required by IECC Section 705.2.1.

Sheet E6

Provide the lighting load calculation for the building demonstrating compliance with IECC Section 705.4 and Table 705.4.

It does not appear the load from electrical panel 114 has been calculated into the total load calculation. Additionally, there does not appear to be a Panel Schedule for Panel 114 or FHP. Please clarify. Reference IBC Section 106.1.1.


ACCESSIBILITY COMMENTS:

Sheet A1.1

Please provide a section through the platforms demonstrating compliance with the provisions ADAAG for access and 1003.3.3.3 for stairs. Reference ADAAG Section 4.1.6 and IBC Section 1003.3.3.3.

Please confirm the latch side/push side clearances for Doors 101G and 101F for conformance with the provisions of ADAAG Figure 4.13.6.

It does not appear that provision have been made to accommodate wheelchair accessibility for participation in facility services. Please clarify. Reference ADAAG Section 4.32.

Please identify the accessible route from the building to the accessible parking facilities and the public way. Reference ADAAG Section 4.6.

Final Status

Task End Date Reviewer's Name Type of Review Description
02/20/2004 TAMI ACHONG OUT TO CUSTOMER Completed