Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T04CM00170
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/15/2004 | JIM EGAN | FIRE | REVIEW | Approved | |
01/15/2004 | PETER MCLAUGHLIN | ZONING | REVIEW | Approved | |
01/22/2004 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Revise the water pressure calculations to include a minimum pressure of 15 PSI. Revise pipe sizes as required. Reference Section 608.1, UPC 1994. 2. Revise flow rate of lavatories to comply with ARS 45-313. 3. Revise fixture unit calculations using the fixture units shown in Tables 6-3 and 7-3, UPC 1994. 4. Show route and termination of T&P relief piping from water heaters. Reference Section 608.5, UPC 1994. 5. Show how the existing 4"S terminates on the North side of the building. Show the upper terminal cleanout. Reference Section707.4, UPC 1994. |
01/22/2004 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Z_DO NOT USE | |
01/22/2004 | ROBERT SHERRY | WATER | REVIEW | Approved | |
01/22/2004 | PATRICIA GILBERT | ENGINEERING | REVIEW | Approved | |
01/22/2004 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide ventilation calculations for project. 2. Revise termination of condensate drains for ACU-7 and ACU-8 to avoid surface runoff. |
03/16/2004 | EGRANT1 | BUILDING-COMMERCIAL | REVIEW | Needs Review | |
03/16/2004 | EGRANT1 | WWM | REVIEW | Needs Review |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
03/16/2004 | EGRANT1 | OUT TO CUSTOMER | Completed |