Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T04CM00010
Parcel: 13510150R

Review Status: Completed

Review Details: 3RD PARTY REVIEW-REVISION/OTHER-2ND

Permit Number - T04CM00010
Review Name: 3RD PARTY REVIEW-REVISION/OTHER-2ND
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/23/2004 STANTEC 3RD PARTY REVIEW-COMMERCIAL REVIEW Denied Plan review for the above-referenced project has been completed, per the 2000 IBC and IMC, 1998 IECC and ICC/ANSI A117.1, 1999 NEC, with all local amendments and the 1994 UPC with Arizona State Amendments. This letter reflects comments to be addressed with a written response to each of the noted items indicating the action taken. In order to facilitate a shorter back-check time, we request that you please provide revised plans and calculations, highlighting any changes that have been made.

SCOPE OF REVIEW:

The scope of this review covers Architectural, Structural, Plumbing, Mechanical and Electrical. All features were checked only to the extent allowed by the submittal provided. All portions of the project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval.

GENERAL:

There are no general comments to be addressed.

ARCHITECTURAL:

There are no architectural comments to be addressed.

STRUCTURAL:

There are no structural comments to be addressed.

MECHANICAL:

There are no mechanical comments to be addressed.

PLUMBING:

There are no plumbing comments to be addressed.

ELECTRICAL:

Now that a sump pump is being added to the scope, where is the electrical service for this pump? Please provide.

Final Status

Task End Date Reviewer's Name Type of Review Description
03/23/2004 TAMI ACHONG OUT TO CUSTOMER Completed