| 07/12/2004 | ANDREW CONNOR | NPPO | REVIEW | Denied | Note on plan: This site is subject to the provisions provided in the CITY OF TUCSON DEVELOPMENT STANDARD NO. 9-04.3.2.A & B HILLSIDE DEVELOPMENT SITE IMPROVEMENT Vegetation Retention and Revegetation. A. Vegetation Retention. 1. Existing trees with four (4) inch or greater trunk diameter and cacti will be preserved in their original locations, except for building sites and access and utilities serving building sites. 2. When retention of the above trees and cacti in their original locations is not possible due to building site location, the trees and cacti will be salvaged and replanted in areas requiring revegetation, whenever possible. B. Revegetation. All cut or fill slopes, which are no steeper than three horizontal to one vertical (3:1) and all utility trenches or septic leaching fields which are not located in parking or driveway areas will be revegetated in compliance with the following requirements. 1. All plants used in revegetation must be the same as the native vegetation on the site or any adjacent site prior to grading or clearing. 2. Revegetation will be accomplished with the following minimum requirements for plants. a. Desert trees, a minimum of fifteen (15) gallon size with a minimum trunk diameter of two (2) inches measured at the soil level, or large specimen cactus will be placed at the same vegetation density found on the site prior to any clearing, grubbing, or grading. b. Seeds for trees, desert shrubs, and grasses will be planted with a density adequate to control erosion and may use one of the following methods of planting or any other method approved by the Zoning Review Section at DSD. 1) Raked into the soil with appropriate mulch materials; 2) Hydroseeding; 3) Anchored mulches; or 4) Established on jute, rolled straw, or similar material. 3. A temporary watering system must be installed until the revegetation materials are established. |
| 07/26/2004 | Paul Machado | ENGINEERING | REVIEW | Denied | To: Kelly Hales DATE: July 26, 2004 Design Solutions 3522 E. Grant Road Tucson, Arizona 85716 SUBJECT: Damiani Residence Grading Plan T04BU01694 (First Review) T14S, R15E, Section 36 RESUBMITTAL REQUIRED: Grading Plan and Drainage Statement. The Grading Plan (GP) and Drainage Statement (DS) cannot be approved as submitted. Please address the following review comments prior to the next submittal. Grading Plan: 1. Grading plan clearly marked "GRADING PLAN". 2. Please include a response letter to the comments along with the corrected copies of the GP. 3. No grading is allowed in the 25% or greater slope area please remove any slopes and/or retaining wall in the restricted area. 4. Show all slopes and the ratio, ie: 3:1, 4:1 etc….. 5. Add note: "Depress all landscaped areas a maximum of 6" for water harvesting" 6. List administrative address/site address on plans. 7. List Development (T04CM02288) number on all sheets. 8. Provide a Location Map (3" = 1 mile). 9. Use Engineering Scale only. 10. Show all symbols in the legend. 11. List all Cut and Fill quantities in cubic yards. If both are 0 cy, please list. 12. Show cross section with transverse and longitudinal slopes. 13. Call out surface paving material. 14. A permit or a private improvement agreement will be necessary for any work performed within the Right-of-way. Contact Permits and Codes at (520) 791-5100 for permit information. 15. Call out the names of all washes. 16. Show the 100-year flood peak discharge. 17. Call out all slopes and stabilization material (concrete, riprap, gabbions or vegetation). 18. Slopes of 3H: 1V require hand placed riprap. 19. Slopes of 2H: 1V or greater require grouted riprap. 20. Cut or fill slopes require a 2' minimum setback from property line. 21. Flow arrows, grades and flow rates within and adjacent to site to show drainage scheme. Drainage Statement: 1. A Drainage Statement is required. A DS is a brief description of drainage conditions applicable for a site which is not affected be 100-year flows of 100 cfs, or more, and is neither subject to detention requirements nor impacted by flows from a significant watercourse per S.M.D.D.F.M., chap. II, 2.1.3. 2. The content and format of the DS should follow S.M.D.D.F.M., chap. II, 2.1.3. 3. Show the project address on the cover of the Drainage Statement. If you have any questions, I can be reached at 791-5550 x1193 or Paul.Machado@tucsonaz.gov Paul P. Machado Senior Engineering Associate City of Tucson/Development Services Department 201 N. Stone Avenue P.O. Box 27210 Tucson, Arizona 85726-7210 (520) 791-5550 x1193 office (520) 879-8010 fax |
| 08/10/2004 | MICHAEL ST. PAUL | ZONING | REVIEW | Denied | Engineering approval required before zoning approval. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 08/16/2004 | DELMA ROBEY | OUT TO CUSTOMER | Completed |