Review Date Reviewer's Name Type of Review Description Status Comments
07/27/2004 Joseph Linville NPPO REVIEW Denied Submit approved site, landscape, and, if applicable, native plant preservation plans.
08/04/2004 BLANCA ESPINO ENGINEERING REVIEW Denied Grading Plan
1. Please include a response letter with the next submittal that states how all comments have been addressed and include copies of the most recent rejected plan pages for comparison.

2. Two clean copies of the approved and stamped development/site plan must be included with grading plan.

3. Indicate all existing and proposed buildings and structures, including roof slope and location of downspouts. D.S. 2-02.2.1.A.6 Indicate roof direction/drainage. Indicate a dimensioned detail of downspout and a symbol to be placed in the legend of symbols.

4. Indicate drainage patterns, proposed finish floor elevation(s) and finish grades. D.S. 2-02.2.1.A.16 Indicate adjacent grades. As per revision note "All sidewalks are 4" above PAALs" in comparison to the proposed grades, there is a discripency between the two.

5. Sidewalks shall be flood free for all storm discharges of up to a 10-year flood event. D.S. 2-08.4.1.E

6. Composition. Sidewalks will be constructed of: Portland cement concrete, four inches thick, with a smooth or broom finish or brick pavers set in a bed of cement. D.S. 2-08.5.1.C.1-3

7. Onsite discharge is not to impact adjacent properties. Demonstrate proposed drainage solutions, such as origin, direction, and destination of flow and method of collecting and containing flow.

8. Indicate spot elevations for walkway and asphalt. Verify FFE against drainage flow line elevation adjacent to pedestrian walkway. Indicate grade break. Indicate FFE for units 6 through 11. Refer to grading plan to indicate elevations.

9. Indicate pedestrian walkway unimpeded around gas meter at Unit #2 (existing).

10. Indicate dimensioned cross section details for basins, drainage inlets/outlets, and wall openings (weep holes).

11. Indicate a dimensioned cross section detail of catch basin on detail 4/C2.

12. Indicate existing and proposed walls. Identify wall as per wall symbol. Include property line and dimension weep hole on wall detail. Structures over 30" high are not to be placed in the sight visibility triangle. Correct and revise.
08/22/2004 David Rivera ZONING REVIEW Denied August 22, 2004

Development Services Department
Zoning Review Section

David Rivera
Senior Planner

Comments:

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering and Landscape Review Section and approval of the site plan.

2. Two copies of the approved and stamped site plan, landscape and NPPO plans must be included with grading plan.

3. The access ramp at the northwest corner of the driveway entrance must be revised to provide an accessible path to the street sidewalk and the on site sidewalk. The proposed ramp only appears to provide a sloped access to the west side of the on street sidewalk and the wing is towards the on site sidewalk. Please revise and the access ramp and show a detail drawing for the ramp in question.

Final Status

Task End Date Reviewer's Name Type of Review Description
08/23/2004 LISA LESNY OUT TO CUSTOMER Completed
08/23/2004 ANGIE SHOFFSTALL REJECT SHELF Completed