Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T03CM05574
Parcel: 11713061K

Review Status: Completed

Review Details: 3RD PARTY REVIEW-COMMERCIAL TI

Permit Number - T03CM05574
Review Name: 3RD PARTY REVIEW-COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/19/2004 STANTEC 3RD PARTY REVIEW-COMMERCIAL REVIEW Denied SCOPE OF REVIEW:

The scope of this review covers Architectural, Structural, Plumbing, Mechanical and Electrical. All features were checked only to the extent allowed by the submittal provided. All portions of the project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval.

GENERAL:

q There are no general comments to be addressed.

ARCHITECTURAL:

q Check the hardware schedules. Some of the doors indicated as receiving special hardware on the plans are not indicated as such on the door schedule. Please coordinate. A review of the Sheets E-3 and E-4 makes the locations of keypads more clear (i.e. the hardware on egress doors cannot require any special knowledge [2000 IBC Sec. 1003.3.1.8]). This previous comment has not been addressed. Specifically, doors 101B and 243 are indicated to have a sign indicating that these exit doors are to remain unlocked during business hours. The exception that allows such a sign is for "main exterior doors" and not for a door along a corridor that egresses into an exit stair. At doors 101B and 243, is the keypad must be for entry and not exit. Doors 101A, 201B, are signed as exits as well, so they also cannot have a keypad required to exit. Please correct.

q The corridor that serves the building south of the southern most exit stair is a dead end corridor. As such it is limited to 50 feet (considering there is a sprinkler system) [2000 IBC Sec. 1004.3.2.3]. The dead end is currently 65 feet long. Please correct. This previous comment has not been addressed. See the attached diagram for clarification regarding this comment.

STRUCTURAL:

q There are no structural comments to be addressed.

MECHANICAL:

q There are no mechanical comments to be addressed.

PLUMBING:

q There are no plumbing comments to be addressed

ELECTRICAL:

q There are no electrical comments to be addressed.

-End of Review
01/20/2004 EROSE1 WWM REVIEW Needs Review
01/20/2004 EROSE1 FIRE REVIEW Approved
01/20/2004 EROSE1 WATER REVIEW Needs Review

Final Status

Task End Date Reviewer's Name Type of Review Description
01/20/2004 ELAINE ROSE OUT TO CUSTOMER Completed