Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: 3RD PARTY REVIEW-COMMERCIAL
Permit Number - T03CM05425
Review Name: 3RD PARTY REVIEW-COMMERCIAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 12/09/2003 | EROSE1 | WWM | REVIEW | Needs Review | |
| 12/09/2003 | EROSE1 | ENGINEERING | REVIEW | Needs Review | |
| 12/09/2003 | STANTEC | 3RD PARTY REVIEW-COMMERCIAL | REVIEW | Denied | SCOPE OF REVIEW: The scope of this review covers Architectural, Structural, Plumbing, Mechanical and Electrical. All features were checked only to the extent allowed by the submittal provided. All portions of the project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval. GENERAL: q There are no general comments to be addressed. ARCHITECTURAL: q There are no architectural comments to be addressed. STRUCTURAL: q Provide a City of Tucson special inspection certificate for the following [2000 IBC Chapter 17]: · Engineered Fill · Concrete · Field Welding · Masonry · Epoxy Anchors q The B5 beam located below the grid intersection B1 appears incorrect. A B5 beam is a 2 1/2" x 27" glue laminated beam. The calculations indicate a 5 1/8" x 12" glue laminated beam. Please clarify. q Page R33 of the calculations indicates that purlin P3 is to have a 1 1/4" camber, while Sheet S2.2 the equivalent purlin (listed as Beam B3) indicates a camber of 1 1/2". Please clarify. q Page R62 of the calculations indicates a 5 1/8" x 12" glue laminated beam. However a 2 1/2" x 27" glue laminated beam is shown on the framing plan on Sheet S2.2 (located on the drive-up canopy as a B5). Please clarify. MECHANICAL: q Provide on the plans a demonstration that outside air is being provided in quantities required by code [2000 IMC Table 403.1]. PLUMBING: q There are no plumbing comments to be addressed. ELECTRICAL: q There are no electrical comments to be addressed. -End of Review- |
| 12/09/2003 | ELAINE ROSE | ZONING | REVIEW | Needs Review | |
| 12/09/2003 | EROSE1 | WATER | REVIEW | Needs Review | |
| 12/09/2003 | EROSE1 | FIRE | REVIEW | Needs Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 12/09/2003 | ELAINE ROSE | OUT TO CUSTOMER | Completed |