Permit Number: T03CM05410
Parcel: 133452230

Address:
35 N HOUGHTON RD

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T03CM05410
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/21/2004 Robert Sherry PLUMBING-COMMERCIAL REVIEW Denied 1. Revise the site drawing on sheet P1.1 to show the size of both the water meter and the reduced pressure backflow preventer assembly. Reference Section 103.2.3, UPC 1994.
2. Provide a site drawing showing the size and route of the building sewer. Show that the building sewer complies with Section 719.0, UPC 1994. Reference Section 103.2.3, UPC 1994.
3. Provide a fixture description for the water closet. The model number shown for the new fixture is for a flush valve, not a water closet. Show the minimum operating pressure for the new water closet. Reference Section 401.1, UPC 1994.
01/21/2004 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Revise the submitted energy code compliance calculations for the building envelope as required. The envelope compliance statement indicates "UNKNOWN (insufficient data)". Reference Section 101.2, International Energy Conservation Code 1998.
2. Revise the ventilation calculations using the occupant loads from Table 403.3, IMC 2000. Reference Section 403, IMC 2000.
3. Revise the smoke detector note on sheet M-2 to indicate that the required smoke detectors are to be located in the return ducts.
01/23/2004 RAUL PALMA BUILDING-COMMERCIAL REVIEW Approved
02/02/2004 Patricia Gehlen ZONING REVIEW Denied Zoning
2/2/2004
1) Two complete sets of the approved development and landscape plans must be included in the submittal package (one for each set of the building plans). A Yellow site card and routing must also be provided,
2) The proposed exterior colors show on sheet A2.1 of the building drawings do not match the SCZ colors approved on the development plan,
3) The square footage of the building on the building plans is larger than the square footage of the building on the development plan. Revise one or the other for consistency.
02/02/2004 Linda Buczynski ELECTRICAL-COMMERCIAL REVIEW Approved
02/04/2004 GERRY KOZIOL WWM REVIEW Denied Need to show location/method of connection to public sewer. May need to build on-site private sewer for Eastpoint Commercial Center (with DEQ review/approval). Need copy of on-site private sewer - manhole or tap permit?

Final Status

Task End Date Reviewer's Name Type of Review Description
02/05/2004 LISA LESNY OUT TO CUSTOMER Completed
02/04/2004 ANGIE SHOFFSTALL REJECT SHELF Completed