Permit Number: T03CM05055
Parcel: 10603066A

Review Status: Completed

Review Details: SITE

Permit Number - T03CM05055
Review Name: SITE
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/29/2003 JIM TATE ENGINEERING REVIEW Denied DATE: October 29, 2003
ACTIVITY NUMBER: T03CM05055
PROJECT NAME: Southern Arizona Vet Specialist
PROJECT ADDRESS: 141 E Fort Lowell
PROJECT REVIEWER: James C. Tate, P.E.

The following items must be revised or added to the site plan. Please include a response letter with the next submittal that states how all comments have been addressed.

Resubmittal Required: Site Plan

Comments

1. Sidewalks must be physically separated from any vehicular travel lane by means of curbing, grade separation, barriers, railings or other means. Keynote 22 (?) states that the proposed sidewalk is at grade. Correct. DS 2-08.4.1

2. The new proposed sidewalk is directly in the path of the solid waste vehicle pickup area. Barriers need to be provided to prevent the dumpster from being pushed on to the sidewalk.

3. Place a note on the plan that all roof downspouts will be routed under any adjacent sidewalk. Sidewalks must be flood free for up to the ten year event.

4. Show roof drainage for the proposed addition.

5. A Flood Use Permit is required prior to Site Plan approval.

6. The Finish Floor Elevation shown on the Site Plan must be as high or higher than that specified on the approved Flood Use Permit and Elevation Certificate. If a datum conversion has been used the appropriate conversion calculation must be included on the plan.

7. An Elevation Certificate must be completed and returned to the Engineering Section prior to final inspection, occupancy of the structure, or issuance of Certificate of Occupancy.

James C. Tate, P.E.
Civil Engineer
10/29/2003 JIM TATE SANITATION REVIEW Denied See Engineering comments.
11/21/2003 Joseph Linville LANDSCAPE REVIEW Approved prev. dev. site
11/24/2003 PETER MCLAUGHLIN HANDICAP-SITE REVIEW Approved
11/24/2003 Peter McLaughlin ZONING REVIEW Approv-Cond SITE PLAN TRANSMITTAL

TO: Kevin Petrick
11635 E. Tanque Verde Rd
Tucson, AZ 85749
(520) 749-2340

FROM: Peter McLaughlin
Senior Planner
Development Services Dept.

FOR: Patricia Gehlen
Principal Planner
Development Services Dept.

PROJECT:
T03CM05055
141 E. Ft. Lowell Rd
Site Plan Review

TRANSMITTAL: November 24, 2003

Upon completion of the following revision/addition, an over the counter review may be arranged to obtain stamped approval by the zoning review section without resubmitting the site plan. The following item must be revised on or added to the site plan:

1. The site plan keynotes do not line up correctly with their corresponding numbers on sheet C.1, making it difficult to read which number applies to the keynotes. Please revise.


If you have any questions about this transmittal, please call Peter McLaughlin, (520) 791-5608.
11/24/2003 JOE LINVILLE NPPO REVIEW Approved Exception per prev. site plan.
12/05/2003 JIM EGAN FIRE REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
12/09/2003 TAMI ACHONG OUT TO CUSTOMER Completed
12/05/2003 ANGIE SHOFFSTALL REJECT SHELF Completed