Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T03CM04982
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/16/2004 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Comment not addressed. Revise ventilation calculations for areas served by a common air handler. Reference Section 401, IMC 2000. |
04/16/2004 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Coordinate the size of the water line feeding the central plant enclosure as shown on the plumbing site plan with the size shown on the central plant enclosure drawing. |
04/19/2004 | MARTIN HAEBERLE | BUILDING-COMMERCIAL | REVIEW | Denied | As discussed this afternoon with Mr. Bollin the following items need to be addressed: 1.Electrical plans examiner pointed out a site light pole is over 20 feet. Structural plans and drawing will be required for this pole. Please submit for review. 2. Items previously addressed as of e-mail dated 1/8/04 are not incorporated in these plans. see below Martin: Happy New Year! I will be in Tucson tomorrow and would like to submit the information that is listed below to get the structural and architectural approval of the plans. Please let me know if you are in the office in the late morning or early afternoon. Thanks, Robert 714-504-1982 -----Original Message----- From: Martin Haeberle [mailto:MHaeber1@ci.tucson.az.us] Sent: Friday, January 02, 2004 1:46 PM To: Robert Bollin Cc: David Mann Subject: Jim Click Ford Robert, I have received and reviewed the revised mezzanine calculations and found them in compliance with the IBC. As discussed with Mr. Mountjoy and Mr. Flynn, the following will be incorporated into the plans: 1. Details reflecting penetration of the 2 hour assembly to reference fire penetrations criteria specified within plans. 2. Remove statement in regards to having less than 15 employees exempts them from providing male/ female restrooms. Upon formal submittal of the final documents, with these revisions, the architectural/ structural portion of the plans are approved. If I can be of further assistance please feel free to contact me. Martin |
04/20/2004 | GERRY KOZIOL | WWM | REVIEW | Denied | Bldg 1 - Jim Click Ford Dealership - includes central plant enclosure 4"CS and Bldg 2 - Car wash. Needs WW/WC Tom Tomchak review of sand/oil interceptor - 579-5771 Needs WW review of connection to public sewer and review of status of existing on-site public sewer-8th floor - 740-6500 Needs WW/review of credit if applicable (no demo drawings) non-par unless WW reviews differently. |
04/20/2004 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Approved | TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL. PLEASE CALL AT 791-5550 X1106 OR EMAIL AT LBUCZYN1@CI.TUCSON.AZ.US IF YOU CARE TO DISCUSS. Sheet E-1 1. In Keynotes 6, 7, 9 & 10, specify that the combination starter shall have overload protection, sized per manufacturer's recommendations. Having run a few calculations, it appears that the circuit breakers in Panels HP and LP are oversized to provide overload protection for these motor loads. They are sized properly for Ground Fault and Short Circuit protection only. Sheet E-3 1. Feeder on the secondary to 15 KVA X'FMR, #10 GND is undersized. Smallest size per Table 250-66 is #8. Please note that, per Footnote 1 of Table 250-66, this Table applies to derived conductors of separately derived ac systems. Since there is no overcurrent protective device ahead of the transformer secondary conduit, Table 250-122 can not be used in this application. 2. Feeder on the secondary to 300 KVA X'FMR, 2/0 GND is undersized. Should be 3/0 per Table 250-66. 3. Feeder on the secondary to 225 KVA X'FMR, 1/0 GND is undersized. Should be 2/0 per Table 250-66. Sheet E9 1. Provide overload protection for Air Compressor on Building #2 Power Plan, and all such equipment on this sheet. This may clear up after the clarification required in Comment #1 above is made. Same for the Dryer. Sheet E-16 1. Provide calculations for both poles and foundations for any pole exceeding 20' in height. Needs approval from Martin Haeberle. 2. According to the Lighting Ordinance, Table 5, as applicable to this Area, any metal halide lighting source over 50W shall have full cutoff lighting distribution. As 175 W uplights, Fixtures K do not comply. |
04/28/2004 | DAVID RIVERA | ZONING | REVIEW | Denied | Two copies of the approved and stamped site plan and related sheets ust be included with the building plans packet. Zoning will review and approve the building plans once the structural and commercial reviewers have approved the building plans. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
04/29/2004 | TAMI ACHONG | OUT TO CUSTOMER | Completed |
04/28/2004 | ANGIE SHOFFSTALL | REJECT SHELF | Completed |