Permit Number: T03CM04380
Parcel: 137339090

Review Status: Completed

Review Details: 3RD PARTY REVIEW-COMMERCIAL TI

Permit Number - T03CM04380
Review Name: 3RD PARTY REVIEW-COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/15/2003 DHERRON1 WWM REVIEW Needs Review
09/15/2003 DHERRON1 ZONING REVIEW Needs Review
09/15/2003 WILDAN 3RD PARTY REVIEW-COMMERCIAL REVIEW Denied The initial review for the above project has been completed. This letter reflects comments which need to be addressed by a written response to each, indicating action taken. In order to facilitate a shorter back-check time, we request that you please provide two (2) sets revised plans and calculations, highlighting any changes with appropriate revision number, revision date and "cloud bubbles." Please return redline drawings with your resubmittal.


Occupancy
Occup. Load
Construction
Area S.F.
Sprinklered
Alarms

M
5,131
II-B
222,697
Yes
Yes


GENERAL COMMENTS:

1. This project has been reviewed for conformance with the 2000 IBC, 1997 UAC, 2000 IMC, 1998 IECC, 1999 NEC codes with local modifications, and the 1994 UPC with State of Arizona Amendments. Any revisions to this plan will require an additional review and approval by Willdan.


ARCHITECTURAL COMMENTS:

Sheet T1.0

1. Under general heights and area limitations. Note 1 story max. Reference IBC Section 507.2.

Sheet A1.0

1. Clarify detail reference on north wall east of grid line 8. Reference IBC Section 106.1.1.

2. Clarify detail reference along grid line 3.75 between grid line E and F. Reference IBC Section 106.1.1.

3. Egress cannot be directed through Door 17A Equipment Area and HAZ Mat Area. Reference IBC Section 106.1.1.

4. Label all rooms as to their use, including those in the area identified as "No Work This Area." Reference IBC Section 106.1.1.

Sheet A6.0

1. Include Door 17F in Door Schedule.

2. Provide specific information related to the door hardware in the schedule, i.e. panic devices, L hardware, etc, for all doors. Reference IBC Sections 106.1.1 and 1003.3.1.8.


STRUCTURAL COMMENTS:

1. Special Inspection appears to be required but not specified on plans for CMU wall construction and welding. Please clarify. Reference IBC Section 1704.1.

2. Deferred submittals appear to be intended but not specified on plans for the following items: Steel joists, steel moment connections, and garden shade structure. Please clarify. Reference IBC Section 106.3.4.2.

Sheet S0.1

1. Please provide a completed City of Tucson Special Inspection Form identified in the required special inspections, i.e., masonry, concrete, welding. Reference IBC Section 1704.

Sheet S-1.0

1. Detail section cuts 10/S-3.0, 13/S-3.1, and 2/S-3.1 appear to be missing from the detail sheets. Please clarify. Reference IBC Section 106.1.1.

2. There appears to be no structural calculations for the footings supporting the garden center roof. Please clarify. Reference IBC Section 106.1.1.

3. Continuous wall footing marks for new CMU wall construction appear to be missing from the foundation plan. Please clarify. Reference IBC Section 106.1.1.

Sheet S-2.0

1. Detail reference bubbles 4/S-4.1 and 7/S-4.1 at the lumber canopy appear to be mislabeled. Please clarify. Reference IBC Section 106.1.1.

2. New and replaced roof top mechanical units appear to be missing the structural operating weight information on the mechanical plans. Please clarify. Reference IBC Section 106.1.1.

3. There appears to be an interior CMU wall along grid A between grids 6.3 and 14.6 that has no structural calculations or structural details. Please clarify. Reference IBC Section 106.1.1.

4. There appears to be no structural details for the new canopy framing between grids 9.2 and 10.2. Please clarify. Reference IBC Section 106.1.1.

5. The CMU wall column supporting lintel beams LB2 and LB10 along grid K appears to be inadequate for combined gravity and lateral loads. Please clarify. Reference IBC Section 106.1.1.

6. There appears to be no structural calculations for the CMU wall along grid H.6. Moment connections of the roof joists to the CMU wall appear to be missing from the plans as well as CMU wall analysis to resist the applied moments. Please clarify. Reference IBC Section 106.1.1.

7. Roof framing note #7 appears to be mislabeled. Please clarify. Reference IBC Section 106.1.1.

8. Lintel beams LB8 along grid #15 appear to be missing from the structural calculations. Please clarify. Reference IBC Section 106.1.1.

Sheet S-3.1

1. Vertical wall reinforcement notes appear to be missing from sheet S-1.1 as noted on detail #1 this sheet. Please clarify. Reference IBC Section 106.1.1.

Sheet S-4.0

1. The note for joist bearing elevations shown on detail #4 appears to mislabel the sheet number. Please clarify. Reference IBC Section 106.1.1.

2. Details #5 and #6 appear to omit the roof decking for the garden center roof. Please clarify. Reference IBC Section 106.1.1.

3. Detail #12 appears to be referenced elsewhere but missing from this sheet. Please clarify. Reference IBC Section 106.1.1.

Sheet S-4.1

1. Detail section #20 appears to be intended as a moment connection but is not labeled that way. Please clarify. Reference IBC Section 106.1.1.

Sheet S-4.2

1. The canopy framing in the vicinity of grids #11.3 and #13.1 appear to be incomplete on detail #1. Please clarify. Reference IBC Section 106.1.1.


PLUMBING COMMENTS:

The plumbing portion has been reviewed and approved.


MECHANICAL COMMENTS:

Sheet M-2

1. Clarify the location and rate for all exhaust fans in restrooms and other locations as may apply. Reference IMC Section 403.1.


ELECTRICAL COMMENTS:

Sheet E-4

1. Identify electrical outlets on roof for servicing of mechanical equipment. Reference IMC Section 306.1.


ENERGY CODE COMMENTS:

The energy code portion has been reviewed and approved.


ACCESSIBILITY COMMENTS:

The accessibility portion has been reviewed and approved.
09/15/2003 DHERRON1 WATER REVIEW Needs Review
09/15/2003 DHERRON1 FIRE REVIEW Needs Review

Final Status

Task End Date Reviewer's Name Type of Review Description
09/15/2003 DHERRON1 OUT TO CUSTOMER Completed