Permit Number: T03CM04365
Parcel: 128100530

Review Status: Completed

Review Details: 3RD PARTY REVIEW-COMMERCIAL

Permit Number - T03CM04365
Review Name: 3RD PARTY REVIEW-COMMERCIAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/23/2003 WILDAN 3RD PARTY REVIEW-COMMERCIAL REVIEW Denied The initial review for the above project has been completed. This letter reflects comments which need to be addressed by a written response to each, indicating action taken. In order to facilitate a shorter back-check time, we request that you please provide two (2) sets revised plans and calculations, highlighting any changes with appropriate revision number, revision date and "cloud bubbles." Please return redline drawings with your resubmittal.


Occupancy
Occup. Load
Construction
Area S.F.
Sprinklered
Alarms

B
132
II-A
13,157
Yes
Yes


GENERAL COMMENTS:

1. This project has been reviewed for conformance with the 2000 IBC, 1997 UAC, 2000 IMC, 1998 IECC, 1999 NEC codes with local modifications, and the 1994 UPC with State of Arizona Amendments. Any revisions to this plan will require an additional review and approval by Willdan.


ARCHITECTURAL COMMENTS:

Sheet A-1

1. Each sheet of the architectural plans must be signed and dated. Reference IBC Section 106.3.4.1.

Sheet A-3

1. Note on plans that egress doors shall be readily operable from the egress side without the use of a key or special knowledge or effort. Exception: The main exterior door is permitted to be equipped with key-operated locking devices from the egress side provided that a readily visible sign is posted stating "This door to remain unlocked when building is occupied." Reference IBC Section A-3.



STRUCTURAL COMMENTS:

The structural portion was reviewed and accepted.


PLUMBING COMMENTS:

The plumbing portion was reviewed and accepted.


MECHANICAL COMMENTS:

The mechanical portion was reviewed and accepted.


ELECTRICAL COMMENTS:

Sheets E-2 and E-3

1. The electrical sheets must be signed and sealed. Reference IBC Section 106.3.4.1.


ENERGY CODE COMMENTS:

The energy code portion was reviewed and accepted.


ACCESSIBILITY COMMENTS:

The accessibility portion was reviewed and accepted.
09/24/2003 TACHONG1 WWM REVIEW Needs Review
09/24/2003 TACHONG1 FIRE REVIEW Needs Review
09/24/2003 TACHONG1 WATER REVIEW Needs Review