Permit Review Detail
Review Status: Completed
Review Details: 3RD PARTY REVIEW-COMMERCIAL TI
Permit Number - T03CM04322
Review Name: 3RD PARTY REVIEW-COMMERCIAL TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/24/2003 | EROSE1 | WWM | REVIEW | Needs Review | |
09/24/2003 | GP | 3RD PARTY REVIEW-COMMERCIAL | REVIEW | Denied | ARCHITECTURAL COMMENTS Sheet A1 1. Please note that the prefab metal stairs will be a deferred submittal. Ref. IBC 106.3.4.2. 2. Clarify if steel storage racks supported above grade will be a part of this project. Ref. IBC 1621.2.8, 1622.3.4 and 2210. 3. No drinking fountain was found on the plan. Clarify how this minimum plumbing facility requirement will be met. Ref. IBC 2902.1. 4. The site plan specifies decomposed granite to the north side of the project. Landings at the floor elevation are required at the doors specified along the north building line. Refs. IBC 1003.3.1.4, 1003.3.1.5. 5. Egress through intervening spaces as shown from the retail through shipping is not permitted. Ref. IBC 1004.2.3. Sheet A2 1. Common use toilet rooms as shown on the second floor are required to be accessible. Ref. IBC 1108.2. 2. Balconies must comply with the provisions of IBC 1406. Sheet A4 1. Show access provisions to concealed spaces as occur above the office areas. Ref. IBC 1208. Sheet A5 1. Please specify the roof covering classification. Ref. IBC 1505. Sheet A6 1. Provide specifications or listing information for the stucco system noted in the elevation drawings. Please show compliance with IBC 1405.14. Sheet A10 1. The note below the floor detail should indicate that the smooth, hard, nonabsorbent surface shall extend 6" up the wall. 5" is specified on the drawing. Ref. IBC 1209. 2. At the door schedule, please note that all egress doors shall be readily openable from the egress side without the use of a key or special knowledge or effort. Ref. IBC 1003.3.18. Sheet A11 1. Please note in the threshold detail 3/A11 that the maximum slope/bevel will not exceed 50%. Ref. IBC 1003.3.1.6. STRUCTURAL COMMENTS General 1. Provide the design and detail of the masonry screen wall shown on the site plan. 2. Coordinate the concentrated loads of rooftop mechanical equipment. Ref. IBC 1606.2. PLUMBING COMMENTS Sheet P1 1. Please provide the material specification for condensate disposal piping. Ref. IMC 307.2.2. 2. Show the termination of the T and P relief valve. Ref. UPC 608. 3. Please show the design for landscape irrigation. 4. Coordinate with architectural comment 3, Sheet A1 for drinking fountain piping. MECHANICAL COMMENTS General 1. Coordinate rooftop mechanical equipment weight specifications with general structural comment 2. 2. Smoke detection system control is referenced to division specifications. This specification was not included in the submittal. Please provide Ref. IMC 606. ELECTRICAL COMMENTS Sheet E1 1. Circuits L8 and L10 were not found. Please show on the plan. Sheets E2 and E4 1. Toilet rooms are shown in the warehouse that do not appear elsewhere in the plan. Please clarify. 2. Circuit L2-31 for rooftop receptacle was not found. Please show on the plan. ENERGY COMMENTS General 1. Please provide energy code compliance data. Interior lighting analysis is approved. |
09/24/2003 | EROSE1 | WATER | REVIEW | Needs Review | |
09/24/2003 | EROSE1 | FIRE | REVIEW | Needs Review |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
09/24/2003 | ELAINE ROSE | OUT TO CUSTOMER | Completed |