Permit Review Detail
Review Status: Completed
Review Details: REVISION
Permit Number - T03CM03500
Review Name: REVISION
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/22/2004 | DAVID RIVERA | ZONING | REVIEW | Denied | August 22, 2004 Development Services Department Zoning Review Section David Rivera Senior Planner Comments: 1. The site plan has been reviewed by the Zoning Section and has been denied due to deficiencies. The owner must apply for Board of Adjustment variances for several items. See site plan comments for more information. 2. The Zoning Review Section has reviewed the building plans but cannot approve them until the revised site plan has been approved by all DSD reviewing agencies. Please include with the building plans two copies of the approved and stamped site plan. A copy of the Board of Adjustment letter must accompany the plans on the next submittal. |
| 09/15/2004 | TERRY STEVENS | BUILDING-RESIDENTIAL | REVIEW | Denied | SPOKE WITH CHAUNCEY MEYERS AS TO CHANGES REQUIRED |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/23/2004 | TAMI ACHONG | OUT TO CUSTOMER | Completed |
| 09/23/2004 | ANGIE SHOFFSTALL | REJECT SHELF | Completed |