Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T03CM03164
Parcel: 12414050A

Address:
1440 E 15TH ST

Review Status: Completed

Review Details: 3RD PARTY REVIEW-CELL TOWER/ANTENNAS

Permit Number - T03CM03164
Review Name: 3RD PARTY REVIEW-CELL TOWER/ANTENNAS
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/08/2003 EROSE1 OPERATIONS REVIEW Needs Review
07/08/2003 STANTEC 3RD PARTY REVIEW-COMMERCIAL REVIEW Denied SCOPE OF REVIEW:

The scope of this review covers Structural and Electrical. All features were checked only to the extent allowed by the submittal provided. All portions of the project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval.

GENERAL:

q There are no general comments to be addressed.

STRUCTURAL:

q There are no structural comments to be addressed.

ELECTRICAL:

q Check the one-line diagram on Sheet E-1 relative to the conductors leading from Panel LP-1 to the ET II Site Support Cabinet. There are 3 conduits carrying conductors for 4 circuits. All conductors are #6 AWG. The breakers protecting these conductors are 50 amps (circuits 5 and 7) and 100 amps (circuits 1 and 3). However, circuits 1 and 3 are noted as a spare so why are conductors being attached to these circuits? Further, the #6 conductors are not capable of taking 100 amps [1999 NEC Table 310-16]. Last, how are these 3 groups of conductors paired for these 4 circuits? Please clarify.
q What sizes are the conductors served by circuits 2 and 4 (the 60 amp AC Surge Protection circuit) and the 20 amp Telco GFI circuit? Please clarify.

-End of Review-
07/08/2003 ELAINE ROSE PLANNING-CITY HALL REVIEW Needs Review
07/08/2003 EROSE1 FIRE REVIEW Needs Review
07/08/2003 EROSE1 ENGINEERING REVIEW Needs Review

Final Status

Task End Date Reviewer's Name Type of Review Description
07/08/2003 ELAINE ROSE OUT TO CUSTOMER Completed