Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: OTHER
Permit Number - T03CM02601
Review Name: OTHER
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/10/2003 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide Listing information for crematory in accordance with UL 791. Reference Section 907, IMC 2000. 2. Provide combustion and dilution air openings to room per Section 703.1, IMC 2000. Two openings are required, one within 12" of the floor and the other within 12" of the ceiling. Each opening shall have a net open area of 1 square inch per 4,000 BTUH of the input rating of the crematory. 3. Provide a detail of the installation of the hot air duct, including the termination of the duct. Reference Section 302.3, Uniform Administrative Code, 1997. |
06/10/2003 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide calculations for the sizing of the natural gas distribution system. Include the natural gas input requirements of all of the connected equipment and their pressure requirements in the calculations. Reference Section 302.3, Uniform Administrative Code, 1997. 2. Provide a natural gas regulator as required by manufacturer of the crematory and show installation of the regulator that conforms to Section 1218.0, UPC 1994. |
06/18/2003 | Martin Haeberle | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Provide structural calculations for proposed addition and new opening in existing wall 2. Indicate pitch of roof and minimum allowed for proposed steel corrugated roof. Reference section 1507.4 IBC 3. How is flashing to be achieved at intersecting roofs? 4. Indicate on plans minimum floor thickness for proposed crematory. 5. Show on plans required roof flashing for crematory stack. 6. Occupancy classification of this space to be an F-1. Revise code analysis data sheet. 7. Provide a complete code analysis data sheet including existing building. |
06/20/2003 | BOB SUBA | ELECTRICAL-COMMERCIAL | REVIEW | Denied |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
06/20/2003 | TAMI ACHONG | OUT TO CUSTOMER | Completed |
06/20/2003 | ANGIE SHOFFSTALL | REJECT SHELF | Completed |