Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: SITE-2nd
Permit Number - T03CM02020
Review Name: SITE-2nd
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/14/2003 | JIM EGAN | FIRE | REVIEW | Approved | |
05/20/2003 | LOREN MAKUS | ENGINEERING | REVIEW | Denied | DATE: May 22, 2003 TO: Mr. Hank Krzysik SUBJECT: Our Lady of Sorrows School Office Site Plan Review REVIEWER: Loren Makus ACTIVITY NUMBER: T03CM02020 SUMMARY: The Site Plan was received by Engineering on April 1, 2003. Development Services Department Engineering Division has reviewed the site plan. The site plan was not approved. Please address the following comments. Site Plan Comments: 1) Provide a location map. (DS 2-02.1.A.4) 2) Provide lot dimensions and bearings and basis of bearing. (DS 2-02.1.A.5) 3) Provide sight visibility triangles for all adjacent intersections. (DS 2-02.1.A.5) 4) Provide line of sight distances per DS 3-01.53 for MS&R Arterial Street Kolb Road for existing and future sight visibility triangles. (DS 2-02.1.A.10) 5) Show drainage pattern flow arrows, and proposed and existing finish floor elevation and finish grades on site plan. Include roof drainage patterns. Indicate that all flows up to a 10 year event will be conveyed under sidewalks. (DS 2-02.1.A.16 and DS 2-08.5.1.E) 6) Provide estimated cut and fill quantities. (DS 2-02.1.A.17) 7) Show existing contours on site plan. (DS 2-02.1.A.23) 8) Label Kolb Road as an MS&R street. Provide dimensioned right-of way for adjacent streets. (DS 2-02.1.A.19) Revise the site plan to address all of these comments and resubmit two copies for review. Include a letter explaining how each comment has been addressed. Loren Makus Senior Engineering Associate Engineering Division Development Services |
05/29/2003 | JOE LINVILLE | NPPO | REVIEW | Approved | previously developed site |
05/29/2003 | JOE LINVILLE | LANDSCAPE | REVIEW | Approved | |
06/05/2003 | PETER MCLAUGHLIN | HANDICAP-SITE | REVIEW | Approved | |
06/05/2003 | PETER MCLAUGHLIN | ZONING | REVIEW | Denied | TO: Hank Krzysik PO Box 13107 Tucson, AZ 85732 (520) 327-4846 FROM: Peter McLaughlin Senior Planner Development Services Dept FOR: PATRICIA GEHLEN Principal Planner Development Services Dept. PROJECT: T03CM02020 Our Mother of Sorrows Church 1800 S. Kolb Road Site Plan Review (1st review) TRANSMITTAL: June 5, 2003 COMMENTS: Please attach a response letter with the next submittal, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. This project is being reviewed as less than a 25% expansion. DS 2-02 2. Percent expansions are cumulative. Provide a cumulative percent expansion calculation, including all other past expansions of building area, on the site plan. If this proposed expansion in addition to other past phases of expansion add up to greater than 25 percent, further comments may be necessary as a full code compliance review may be required. DS 2-02.2.2. A.6 3. Add the development designator "12" to the site plan. LUC 2.3.4.2.C.4 4. Provide a lot coverage calculation on the plan. The maximum allowed lot coverage is 60 %. LUC 3.2.3.2.A 5. Provide a Floor Area Ratio calculation on the plan. The proposed FAR is calculated as gross floor area divided by site area. The maximum allowed FAR per development designator "12" is 0.40. DS 2-02.2.2.A.2 LUC 3.2.3.2.A 6. It is stated on the plan that the current proposal is under review for a special exception request. Please add to the site plan the SE case number, date of approval, what was approved and any conditions imposed. DS 2-02.2.1.A.38 If you have any questions about this transmittal, please call Peter McLaughlin, (520) 791-5608. |
06/25/2003 | LOREN MAKUS | SANITATION | REVIEW | Passed |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
06/25/2003 | TAMI ACHONG | OUT TO CUSTOMER | Completed |