Permit Number: T03CM00801
Parcel: 13006004A

Review Status: Completed

Review Details: COMMERCIAL NEW

Permit Number - T03CM00801
Review Name: COMMERCIAL NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/05/2003 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied Provide ventilation of the multi-purpose building per Table 403.3, IMC 2000.
03/05/2003 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Increase size of VTR to equal the cross-sectional area of the required building sewer. Reference Section 904.1, UPC.
2. A mop sink is not an approved receptor for a P/T discharge. Reference Section 608.5, UPC.
3. The check valve and shut-off valve, shown at the cold water inlet of the water heater, prevent the proper operation of the thermal expansion tank. Reference Section 608.3, UPC.
4. Provide roof drain design for Health Office addition and P.E. Space building.
03/05/2003 ROBERT SHERRY WATER REVIEW Approved
03/06/2003 JIM EGAN FIRE REVIEW Approved
03/28/2003 BOB SUBA ELECTRICAL-COMMERCIAL REVIEW Denied 1. Install or indicate required maint. receptacles @ mechanical equipment. 2.Indicate grounding electrode system at building MPR.
04/17/2003 MARTIN HAEBERLE BUILDING-COMMERCIAL REVIEW Denied 1. Provide an accessible route to the PE building. Reference section 1104.2 IBC
2. Provide minimum number of accessible entrances per section 1105.2 IBC
3. Landings are required at all exit doors. Reference section 1003.3.1.5 IBC
4. Include allowable area calculations for addition to existing building.
5. Deferred submittal for the metal building requires approval of the Building Official. Submit a letter of request for deferment with approximate time of submittal.
6. Occupant load factor for PE building is 7 per square foot net. Reference table 1003.2.2.2 IBC. Revise calculations
7. Revise plumbing fixture count to reflect Table 2902.1.
8. Door to room 42A does not have the required clearances for accessibility. Reference table 404.2.4.1 ANSI A117.1. Revise plan
9. Storage rooms 101/102 are required to be separated from major use by a one-hour fire partition with 45-minute openings. Reference section 302.1.1 IBC. Provide detail of listed fire wall and location
10. Panic hardware is required on exit doors of PE building. Indicate on door schedule.
11. Centerline of toilet to be a maximum of 18 inches from wall. Reference section 604.2 A117.1 ANSI. Revise plan
05/07/2003 GERRY KOZIOL WWM REVIEW Denied Needs manhole tap permit

Final Status

Task End Date Reviewer's Name Type of Review Description
06/05/2003 LISA LESNY OUT TO CUSTOMER Completed