Permit Number: T03CM00760
Parcel: 13819105A

Address:
430 W ARAGON RD

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T03CM00760
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/27/2003 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Provide calculations demonstrating adequate ventilation. Provide calculations based on the data shown in Table 403-3, IMC 2000. Reference Section 401, IMC 2000.
06/27/2003 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Coordinate plumbing plans with waste and vent riser diagram. Waste branch with urinals and two lavatories are not coordinated.
2. The Fixture Connection Schedule indicates that the fixtures in the apartment are connected to the existing 1-1/4" water main but the floor plans and water isometric do not show any connection. Please clarify.
3. Based on the calculations, the ¾" water meter is too small to provide for the new service. Please revise.
4. Pipe sizing should be limited to 10 FPS or the maximum values given in the appropriate Installation Standard (e.g. copper piping at 5-8 FPS, PVC at 8 FPS). Reference Section A 6.1, UPC 1994.
07/07/2003 Martin Haeberle BUILDING-COMMERCIAL REVIEW Approv-Cond
07/17/2003 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1106 OR EMAIL AT LBUCZYN1@CI.TUCSON.AZ.US
IF YOU CARE TO DISCUSS.

1. Lights are depicted on Panel L Circuit 2 on the Electric Plan. However, on the Panel Schedule, there are only existing receptacles. Please clarify.
2. Keynote 6 in Library calls for a new lighting fixture. Identify panel and circuit number.
3. Show Panel and Circuit Number on the Electric Plan for new GFCI on Keynote 8 Sheet E-101.
4. Identify Panel and Circuit Numbers on the Electric Plan for new Exhaust Fans on Keynote 3 on Sheet E-101.
5. Identify Panel and Circuit Numbers on the Electric Plan for new Vanity Light Fixture on Keynote 9 on Sheet E-101.
6. Electrical Plans show Exhaust Fan in both Ladies and Men's rooms. Machanical Plans show Exhaust Fans in Ladies Room only. Please clarify.
7. Show Stage Lighting Fixture on Fixture Schedule.
8. Regarding Panel L Schedule, provide a load calculation documenting existing load, added load, and removed load. Document that this panel is not overloaded with the addition of the new Panel N. New Panel N is shown in two places; please correct. Water Heater is show bold, suggesting new load; however, the wording states "existing"; please clarify.
9. Line Diagram calls for the installation of #12 G on the load side of a 30A CB. This conductor shall be sized at #10 per NEC Table 250-122. Make the same change on the Electrical Plan.
10. One Line Diagram calls for a new 5 Ton AC Unit. Mechanical Equipment Schedule on Sheet M-102 calls for a 2 Ton Unit. Please clarify.
11. Total load calculation shall take into consideration the power factor of the facility. Peak Load Demand calculations equate Kilowatts with Volt-amperes. Please correct. After Volt-amperes are calculated, the Service may need to be upgradeded with this addition.

Final Status

Task End Date Reviewer's Name Type of Review Description
07/29/2003 TAMI ACHONG OUT TO CUSTOMER Completed
07/17/2003 ANGIE SHOFFSTALL REJECT SHELF Completed