Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T03BU02002
Parcel: 132130580

Address:
1111 E BENSON HY

Review Status: Completed

Review Details: GRADING

Permit Number - T03BU02002
Review Name: GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/15/2003 Loren Makus ENGINEERING REVIEW Denied DATE: August 20, 2003
TO: Jeffrey A. Stanley, PE
SUBJECT: Arizona Truck Center, Grading Plan Review and Site Plan Review
REVIEWER: Loren Makus
ACTIVITY NUMBERS: T03BU02002 and T03CM03885

SUMMARY: The Site Plan and Grading Plan and Stormwater Pollution Prevention Plan (SWPPP) were reviewed by Development Services Department Engineering Division. The Site Plan and Grading Plan were not approved at this time.

Site Plan and Grading Plan Comments

1. Revise the Site and Grading plans to show roof drainage patterns and specify that drainage flowing across all pedestrian circulation paths and sidewalks shall be conveyed under the path or sidewalk for up to ten-year frequency flood events. (DS 2-08.4.1.E and DS 2-08.3.1)
2. Cross section A on page 3 of three does not appear to match the larger plan. Please revise the cross section or the plan to provide consistency.
3. Show distance to driveways on adjacent properties to show that the standards of the Transportation Access Management Guidelines for the City of Tucson (TAMG) are met. The standards require a maximum of 2 driveways in 300 feet of street frontage and a minimum of 80 feet between driveways. (TAMG 5.4.1)
4. Aerial photos of the site appear to show two buildings located on the project site. Address the location and removal of the buildings on the site plan. (DS 2-02.2.1.A.6)
5. Provide the basis of bearing. [City of Tucson Development standard (DS) 2-02.2.1.A.5]
6. Label the Solid Waste Container enclosure. (DS 6-01.4.1.A)
7. Show a 25 foot minimum curb return radii for each driveway location. (TAMG 5.5)

Stormwater Pollution Prevention Plan (SWPPP) Comments

8. Clarify whether Entranco or Jeffrey A. Stanley Engineering is the engineer of record and the operator with "Operational Control over Construction Plans and Specifications." (Part IV.C.1)
9. Include the import of soil in the intended sequence of soil disturbing activities. Also note that the sweeping schedule may have to be increased if tracking of sediments occurs during the soil importation. (Part IV.C.2.b and Part IV.D.1)
10. The Hydrology Report indicates that this project is in the Mission View Wash watershed and the SWPPP identifies the Tucson Diversion Channel as the receiving water. Please clarify or explain the apparent discrepancy. (Part IV.C.4)
11. Show the receiving water on the location map. (Part IV.C.2.e)
12. Specify an inspection schedule of at least once every seven days or once every 14 days and within 24 hours of the end of each storm event of 0.5 inches or greater. The reduced schedule described in the SWPPP may be used during the seasonally dry period of the year. (Part IV.H)
13. Provide signed certifications for each operator. (Part IV.J.1)

Revise the Site Plan, the Grading Plan and the SWPPP addressing all of these comments and resubmit two copies for review along with the drainage report. If you would like to meet with me to discuss any of these comments please call me at (520) 791-5550 ext. 1161.

Loren Makus
Senior Engineering Associate
Engineering Division
Development Services
08/25/2003 PATRICIA GEHLEN ZONING REVIEW Denied Zoning
8/25/2003
Zoning will review and approve the grading plans once Engineering has approved.
09/11/2003 JOE LINVILLE NPPO REVIEW Denied An approved site / native plant preservation plan is required prior to review.

Final Status

Task End Date Reviewer's Name Type of Review Description
09/17/2003 TAMI ACHONG OUT TO CUSTOMER Completed
09/17/2003 ANGIE SHOFFSTALL REJECT SHELF Completed