Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T03BU00941
Parcel: 14117005A

Review Status: Completed

Review Details: GRADING

Permit Number - T03BU00941
Review Name: GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/29/2003 LAITH ALSHAMI ENGINEERING REVIEW Denied Laith Alshami, Engineering and Floodplain Comments, 05/05/2003,


1. The Grading Plan Should be clearly marked "GRADING PLAN"
2. Provide Location Map.
3. Provide a Legend showing all used symbols.
4. Show proposed finished floor elevations for all proposed pads.
5. Demonstrate that the proposed grading will comply with the setback requirements stated in Section 14 of Chapter 36 "Excavation and Grading" of the Tucson Code.
6. 10-year flow has to be completely conveyed under sidewalks via sidewalk scuppers, when the runoff crosses any sidewalk/walkway. This also applies to roof drainage. Identify roof drainage and demonstrate compliance with this requirement.
7. Dimension the proposed detention/retention basin and include all construction details. Identify the exact location of the basin.
8. Show the permanent water-harvesting basins.
9. The Site Plan must be approved before the Grading Plan can be approved.
10. Revise the Grading Plan in accordance with the Drainage Report and Site Plan revisions.
11. The Grading Plan should be detached and submitted separately from the Site Plan. Each of the plans should have the required information to stand on its own.
12. The Horizontal Control Plan should be made part of the Grading Plan.
13. A Stormwater Pollution Prevention Plan (SWPPP, usually pronounced "swip") is required for this project by state regulation (AzPDES).
05/07/2003 JOE LINVILLE NPPO REVIEW Denied Submit copy of the approved NPPO plan. NPPO inspection required prior to plan approval.
05/12/2003 LOREN MAKUS NPDES REVIEW Denied Submit three copies of a stormwater pollution prevention plan and the notice of intent for this project. Details for the SWPPP can be obtained from the ADEQ website at www.adeq.state.az.us/environ/water/permits/stormwater.html
05/13/2003 PETER MCLAUGHLIN ZONING REVIEW Denied Zoning
5/13/2003
Grading plans may not be reveiwed and approved until Engineering has approved the plans

Final Status

Task End Date Reviewer's Name Type of Review Description
05/19/2003 LISA LESNY OUT TO CUSTOMER Completed
05/19/2003 ANGIE SHOFFSTALL REJECT SHELF Completed