Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T03BU00734
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
11/19/2003 | PATRICIA GILBERT | ENGINEERING | REVIEW | Denied | DATE: November 19, 2003 ACTIVITY NUMBER: T03BU00734 PROJECT NAME: Mohave Road Apartments PROJECT ADDRESS: 102 East Mohave Road PROJECT REVIEWER: Patricia Gilbert The following items must be revised or added to the grading plan. Please include a response letter with the next submittal that states how all comments have been addressed. RESUBMITTAL REQUIRED: GRADING PLAN 1. A copy of the stamped approved Site Plan must be included with the Grading Plan submittal. 2. Approval of the Flood Use Permit is required prior to grading plan approval. 3. The proposed FFE and 100-yr. Peak WSEL in the Drainage Report is incorrect. Therefore the FFE on the grading plan is incorrect. Please have the drainage report revised and make the necessary corrections on the grading plan. 4. Development in the floodplain must be constructed so as to protect placed fill from erosion which could be caused by floodwater. Such fill shall be protected from erosion which could be accomplished by placing rip rap, vegetative cover, bulk heading, or any other city approved methods. Floodplain and Erosion Hazard Management, Tucson Code, Chapter 26.5.2.12. The proposed fill around the buildings must be protected from floodwaters. Show the proposed protection. This comment was not addressed. Please address this comment. Comment number 12 states that any slopes steeper than 3:1 shall be protected by approved methods. The grading plan needs to be specific to what type of method will be used for slope protection. Revise the plan. |
12/10/2003 | Joseph Linville | NPPO | REVIEW | Approv-Cond | |
12/10/2003 | DAN CASTRO | ZONING | REVIEW | Denied | Zoning will review and approve the grading plans once Engineering has approved the plans. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
12/18/2003 | DELMA ROBEY | OUT TO CUSTOMER | Completed |