Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL NEW
Permit Number - T02CM05474
Review Name: COMMERCIAL NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/09/2003 | JIM EGAN | FIRE | REVIEW | Denied | 1. Provide information on commodities stored to verfiy S-2 occupancy classification. 2. provide fire sprinkler system design criteria on plan. a. Design standard to be used. b. Hazard classification. c. Minimum design density and area of application. d. Water supply information: Static PSI__ Residual PSI__ Flow__GPM |
| 01/13/2003 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL. PLEASE CALL AT 791-5550 X1106 OR EMAIL AT LBUCZYN1@CI.TUCSON.AZ.US IF YOU CARE TO DISCUSS. 1. Provide specifications for the door operator motors. Current, voltage, horsepower, phase, overload protection. 2. Specify circuit breaker size at panel feeding door opener motors. 3. Specify conductor size and insulation type. 4. Indicate presence and location for switch/disconnect for door operator motors. 5. Specify overload protection for door opener motors, unless provided with the equipment. 6. Provide load calculation accounting for new load on existing panel. |
| 01/30/2003 | RAUL PALMA | BUILDING-COMMERCIAL | REVIEW | Denied | City of Tucson, Development Services BUILDING AND STRUCTURAL COMMENTS 1) a) Povide a complete lateral analysis for the building being enclosed. b) If the existing structure is resisting the lateral shear forces, then show how the forces are being distributed to the existing walls. c) Show the roof diaphragm connections(nails,screws,welding)used to transfer the shear loads to the walls and down to the foundation. 2) Provide the engineering design for the beam supporting the roll-up door. Specify the size and show a connection detail of the beam to the door and to the structure. 3) Resubmit plans for review. |
| 01/31/2003 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 02/03/2003 | MARTIN HAEBERLE | MECHANICAL-COMMERCIAL | REVIEW | Passed | |
| 02/03/2003 | MARTIN HAEBERLE | PLUMBING-COMMERCIAL | REVIEW | Passed | |
| 02/03/2003 | MARTIN HAEBERLE | WATER | REVIEW | Passed | |
| 02/06/2003 | PATRICIA GEHLEN | ZONING | REVIEW | Approved | |
| 02/07/2003 | JAMES TATE | FLOODPLAIN | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 02/10/2003 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |